City of Frisco Question and Answer Board » Archive » Sidewalk connection to Warren Sports Complex from Sunflower Way. « Previous Next »

  Thread Last Poster Posts Pages Last Post
  Start New Thread        

Author Message
 

Matthew Wheaton
New member
Username: Mdwheaton

Post Number: 1
Registered: 12-2004
Posted on Sunday, December 05, 2004 - 09:01 pm:   

Hello,

Is there a plan, or possibility to put a short sidwalk extension from the intersection of Blackberry Lane and Sunflower Way to connect with the main sidewalk in the Warren Sports complex ?
There is an opening in the fence already, and residents use the opening to go to the park, and ride bikes through as well.
The area is heavily trampled and can get very muddy after a rain. It doesn't seem like it would be a great expense to connect that area to the park, since there's already a fence opening there, implying an entrance.

Thank you,
Matthew Wheaton
 

Rick Wieland, Dir. of Parks and Rec
Moderator
Username: Rick

Post Number: 139
Registered: 01-2002
Posted on Tuesday, December 07, 2004 - 10:03 am:   

Matthew,

Thanks for your note regarding a possible trail/sidewalk connection near the intersection of Blackberry Lane and Sunflower Way.

I will be visiting this area today and will look into your request in more detail. I will provide a more detailed response by tomorrow (Wednesday, December 7, 2004).

Thanks for your interest.

Rick Wieland
Director of Parks and Recreation
(972) 335-5517
rwieland@friscotexas.gov

 

Rick Wieland, Dir. of Parks and Rec
Moderator
Username: Rick

Post Number: 142
Registered: 01-2002
Posted on Thursday, December 09, 2004 - 06:02 pm:   

Matthew,

I just wanted to follow up from my message on Tuesday regarding a possible sidewalk trail connection near the intersection of Blackberry Lane and Sunflower Way.

After visiting the site along with our Parks Superintendent, we feel that this might be a possible miscellaneous project that could be provided at the location you had mentioned in your note.

We are looking at the site and seeing what can be done to provide a connection on that end of the park to the sidewalk trail that currently exists just to the north of the existing sidewalk.

If possible, we will look to adding this section of sidewalk trail during the late winter and early spring.

If you have any additional questions, please feel free to let me or our staff know. Thanks again for the suggestion.

Sincerely,

Rick Wieland
Director of Parks and Recreation
(972) 335-5517
rwieland@friscotexas.gov

 

Matthew Wheaton
New member
Username: Mdwheaton

Post Number: 2
Registered: 12-2004
Posted on Monday, May 16, 2005 - 11:02 am:   

Hi Rick,

Any chance to revive this discussion or if this one will make it into any work in that area this year ?
 

Rick Wieland, Dir. of Parks and Rec
Moderator
Username: Rick

Post Number: 152
Registered: 01-2002
Posted on Tuesday, May 17, 2005 - 03:46 pm:   

Mr. Wheaton,

Sorry about the delay in getting back to you about this subject. To be candid with you, we lost some of our in-house expertise with concrete work over the winter and this project became delayed.

In speaking together with our staff, we are going to look at contracting this out within the next thirty days, depending on the final cost estimate.

After scheduling the project, I don't anticipate that the actual pouring of the sidewalk will take a great deal of time.

Please feel free to give me or Bobby Johnson a call this next week and we hope to be in a position to give you some completion times.

Thanks for your patience,

Rick Wieland
Director of Parks and Recreation
(972) 335-5517
rwieland@friscotexas.gov
 

Matthew Wheaton
New member
Username: Mdwheaton

Post Number: 3
Registered: 12-2004
Posted on Sunday, July 03, 2005 - 10:20 pm:   

Hi Rick,

Any more updates on this one ?

Thanks Rick,
Matthew Wheaton
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 172
Registered: 02-2003
Posted on Tuesday, July 05, 2005 - 09:31 am:   

Matthew,

A purchase order was issued to Jim Bowman Construction Company in June to do the sidewalk installation. I spoke with them last week and they indicated it would probably be late July or early August before the work would be done. Since this is a rather small job, they wanted to coordinate it with some other work in the area.

Please feel free to contact me direct if you would like to discuss further.

Sincerely,

Bob Johnson
Superintendent of Parks
972-335-5517

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Post as "Anonymous"
Enable HTML code in message
Automatically activate URLs in message
Action: