Benjamin Lee
New member
Username: Ag97

Post Number: 1
Registered: 03-2005
Posted on Tuesday, March 15, 2005 - 09:12 am:   

When will Teel be open to four lanes? Traffic has been utilizing a single lane on both sides for a few days...

Thanks so much!

Cissy Sylo, Director of Engineering Serv
Username: C_sylo

Post Number: 53
Registered: 06-2003
Posted on Tuesday, March 15, 2005 - 11:29 am:   

All of the lanes will be open within 2 weeks. The City will partially open a roadway to limited lanes, until all of the motorists are familar with the changes in the lane openings. We don't want someone to turn to the "old" northbound Teel when in reality, that there are now 2 southbound lanes of traffic.

The closure of the lanes also allow the contractor to continue working to complete the final construction items in the median. The contractor is installing street lights over the next several weeks. By opening the road to only 2 lanes we can continue to work on completing the necessary items and allow traffic to safely travel on the new lanes.

Add Your Message Here
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Options: Post as "Anonymous"
Enable HTML code in message
Automatically activate URLs in message