Posted on Monday, July 30, 2007 - 07:11 pm:   

When is Main between Preston and Custer going to be rebuilt?

Elizabeth Metting, City Engineer/AsstDir
Username: Elizabeth_metting

Post Number: 1
Registered: 07-2007
Posted on Tuesday, August 07, 2007 - 12:14 am:   

Ken, The following update is copied from our Engineering Services Monthly report, which is posted on the website with the latest project information every month. Go to Departments- Engineering - Engineeering - Reports. That will let you know the latest on every project being managed by the City Engineering Department.

FM 3537/Main Street (Preston Road Custer Road) Engineering consultant Birkhoff, Hendricks & Conway, LLP, (BHC) has received comments on their 60%-plans from both City staff and TxDOTs Collin Co. Area Office. Revised 60% plans will be resubmitted by October. The project is anticipated to be ready for bidding in September 2008. Once bid, construction is estimated to require twenty-four (24) months. (Project Manager: Toyin Fawehinmi)

Add Your Message Here
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Options: Enable HTML code in message
Automatically activate URLs in message