Posted on Thursday, September 25, 2008 - 04:58 pm:   

Many dates and start times have been thrown around for the start of construction on Eldorado (DNT to Preston), and Preston (Main to 380). Just doing a search, many of the dates I have found mentioned are listed below.

I realize much of the delay is due to TxDot, but it just seems like every so often we have been told that construction would begin within a certain time frame - only to be given a new time frame once that expires.

So, what is the status of these sections of road? When will contruction begin? How long will it take? And they are both going straight to 6 lanes, correct?

February 02, 2002 - Preston not on the TxDot 3-year plan
http://qanda.ci.frisco.tx.us/discus/messages/4141/2745.html

April 01, 2004 - Preston construction is 18 months out
October 14, 2004 - Preston construction is 18 months out
http://qanda.ci.frisco.tx.us/discus/messages/4141/5436.html

September 30, 2004 - Preston construction is 18 months out
http://qanda.ci.frisco.tx.us/discus/messages/4141/6117.html

October 28, 2004 - Preston construction to begin in '06
March 16, 2005 - Preston construction to begin in March '07
http://qanda.ci.frisco.tx.us/discus/messages/4141/6237.html

November 02, 2005 - Eldorado construction West of Preston to begin in about 9 months
http://qanda.ci.frisco.tx.us/discus/messages/4141/7539.html

March 22, 2006 - Eldorado construction to begin about 10 months after May '06
September 04, 2007 - Eldorado to be bid by end of '07
http://qanda.ci.frisco.tx.us/discus/messages/1/7259.html

October 05, 2006 - Eldorado construction to begin in Spring '07
April 10, 2007 - Eldorado construction to begin in Sept '07
February 19, 2008 - Eldorado construction to begin in the Summer ('08)
June 06, 2008 - Preston construction to begin in early '09
June 06, 2008 - Eldorado construction sometime after Fall '08
http://qanda.ci.frisco.tx.us/discus/messages/1/9193.html

June 09, 2006 - Preston "letting" to begin in June '08
June 13, 2006 - Eldorado phase 1 design should be complete April '07
June 13, 2006 - Eldorado phase 2 design should be complete September '07
http://qanda.ci.frisco.tx.us/discus/messages/1/8253.html

September 16, 2008 - Preston construction to begin in early '09
http://qanda.ci.frisco.tx.us/discus/messages/1/27389.html
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 6
Registered: 06-2008
Posted on Friday, October 10, 2008 - 08:41 am:   

The widening of Eldorado Parkway between DNT and Preston to 6 lanes is expected to begin construction in early 2009. There are two reasons for the recent delays to this project. The first is that the project was originally scheduled to be constructed to 4 lanes and widened to 6 lanes in the future. Funding was identified to construct the 6 lane roadway now, so more time was needed to add the additional lanes to the construction plans. Also, an error was discovered in the drainage plans when the existing 2 lanes were constructed. The drainage system had to be reevaluated and additional design work was necessary. These design of these items are being completed and the Right of Way for the project is being acquired. We do not anticipate any further delays and we expect construction to begin in early 2009.

The widening of Preston Road to 6 lanes from Main Street to US 380 is a TxDOT project. The key reason in the delay of this project is the acquisition of the Right of Way for the project. TxDOT is required to follow federal regulations in the acquisition of Right of Way. As a result, the timeline for this process is difficult to predict. Nearly all of the Right of Way has now been acquired and TxDOT is bidding the project on October 15 (next week). You should begin to see utility relocations occurring in the next few weeks and TxDOT's contractor should begin work in Spring 2008, when the utility relocations are completed.

Jason Brodigan
Senior Civil Engineer
 

Razorback
New member
Username: Razorback

Post Number: 11
Registered: 09-2003
Posted on Monday, October 13, 2008 - 10:56 am:   

If the widening is going to happen soon, why is the development on Eldorado across from the Home Depot building a concrete entrance with what appears to be a concrete lane divider? The entrance and divider goes across what appears to the future eldorado lanes and connects with the existing 2 lane road.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 7
Registered: 06-2008
Posted on Monday, October 13, 2008 - 02:54 pm:   

All developments in Frisco are required to have two points of access to the site for fire protection. The driveway being placed across from Home Depot is required to maintain two points of access to the apartment complex. The driveway is being placed as non-reinforced concrete so the driveway can be easily removed during construction of Eldorado Pkwy.

Jason Brodigan
Senior Civil Engineer

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: