Andy Grevsmuehl
New member
Username: Grevsmuehl

Post Number: 3
Registered: 06-2005
Posted on Wednesday, June 08, 2005 - 12:50 pm:   

Are their any current plans to widen Lebanon to 4-lane road from Heritage Lakes to FM423?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 161
Registered: 07-2003
Posted on Wednesday, June 08, 2005 - 01:41 pm:   

Yes, but currently in the second bond fund it is not budgeted. You can go to the Cities web page under Planning and look at the Thoroughfare Plan.
If you need further information please advise, at 972-335-5585-129.
Frank Jaromin
 

Bking
New member
Username: Bking1306

Post Number: 6
Registered: 04-2005
Posted on Thursday, June 09, 2005 - 05:36 pm:   

By the way, When is Lebanon form Dallas Parkway (Tollway) to Legacy going to be a 4 lane street. The lanes start out as 4 lanes at Lebanon/Tollway then goes to 2 lanes at Starwood?
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 40
Registered: 10-2003
Posted on Friday, July 08, 2005 - 09:22 am:   

Thanks for the post Bking. The design for that section of Lebanon is complete and the city is working on acquiring the necessary right of way to construct the road. It is anticipated to start construction in approximately 4 months and take 3 months to complete. If you have any additional questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Paul Sukhu
New member
Username: Paul_s

Post Number: 5
Registered: 12-2004
Posted on Tuesday, October 18, 2005 - 07:57 am:   

What is the status on expanding Lebanon to 4 lanes from Starwood to Legacy?

It doesn't look like any construction has begun.

Thanks.

 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 59
Registered: 10-2003
Posted on Tuesday, October 18, 2005 - 11:09 am:   

Thanks Paul for the post. The design plans are currently being revised in response to an adjacent property owners request in conjunction with acquiring the necessary right-of-way. Once this process is complete the project will be advertised for bidding. It is now anticipated to start construction early next year (February - March) and be complete by summer.

If you have any additional questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

suresh munipalli
New member
Username: Munipalli

Post Number: 1
Registered: 02-2006
Posted on Thursday, February 02, 2006 - 04:36 pm:   

Any update on plans to widen Lebanon to 4-lane road from Heritage Lakes to FM423?
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 75
Registered: 10-2003
Posted on Friday, February 03, 2006 - 08:40 am:   

Thanks Suresh for the post. Staff is currently working with a consultant on the design of Lebanon from Heritage Lakes to a 4 lane divided roadway. As stated by the City Engineer in his 6/8/05 post, the road is currently unfunded. If a proposed bond election is approved by City Council, then the citizens of Frisco will vote whether or not to approve funding for roads sometime early this summer. If the roads package is approved by the voters, construction could begin before the end of the year.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Paul Sukhu
New member
Username: Paul_s

Post Number: 9
Registered: 12-2004
Posted on Tuesday, August 08, 2006 - 05:27 pm:   

There seems to be major contruction on the two lane section of Lebanon in Lone Star Ranch. What is being done?

Thanks.
 

Matt Richardson, EIT
Moderator
Username: Matt_richardson

Post Number: 3
Registered: 08-2006
Posted on Wednesday, August 09, 2006 - 03:01 pm:   

Paul,

The construction you are seeing is actually for a 20" diameter sanitary sewer line. The developers for Lone Star Ranch and surroudning properties are constructing this line to meet the build-out needs for this portion of Frisco.

If you have any additional questions, please feel free to contact the Engineering Services Department at 972-292-5400.

Thanks,

Matt Richardson, EIT
Project Manager, Engineering Services Department
 

Paul Sukhu
New member
Username: Paul_s

Post Number: 10
Registered: 12-2004
Posted on Tuesday, January 16, 2007 - 07:37 am:   

I have heard that Lebanon, east of FM 423, will be widened from 2 to 4 lanes in 2007. What are the details on this? Thanks.
 

Luke Jalbert, EIT
Moderator
Username: Luke_jalbert

Post Number: 7
Registered: 07-2006
Posted on Wednesday, January 17, 2007 - 03:49 pm:   

Mr. Sukhu,
The design for that stretch of Lebanon is completed. We are in the process of obtaining Right-of-Way. This project should go to construction this spring.

Thanks

Luke Jalbert, P.E.
Engineering Services Department
 

David Lacefield
New member
Username: Dlacefie

Post Number: 1
Registered: 02-2007
Posted on Thursday, March 29, 2007 - 02:50 pm:   

Is median lighting for Lebanon between 4th Army and Legacy a part of the project to widen lebanon?
 

Luke Jalbert, EIT
Moderator
Username: Luke_jalbert

Post Number: 9
Registered: 07-2006
Posted on Friday, March 30, 2007 - 03:04 pm:   

Mr. Lacefield,

This project will widen the road to four lanes. From 4th Army, back to the East to where there are 4 existing lanes, lighting will be added.

Thanks

Luke Jalbert, P.E.
Engineering Services Department

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: