Jeff K
New member
Username: Jsk

Post Number: 4
Registered: 12-2004
Posted on Saturday, April 23, 2005 - 08:48 pm:   

Please, give an update on the scheduled completion date for the construction on 720, just west of Custer?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 154
Registered: 07-2003
Posted on Monday, April 25, 2005 - 09:02 am:   

Staff has just received bids for the construction of the intersection at Custer Road and FM 3537 last week. This bid is going to City Council on May 3, 2005 for approval and normally it requires 60 days to see construction start with a 6 month construction schedule. We anticipate the opening of this to be in January 2006.

If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer

 

Ed Thompson
New member
Username: Ethompson

Post Number: 3
Registered: 11-2004
Posted on Monday, April 25, 2005 - 10:41 am:   

It was my understanding that 3537 was under the control of TXDOT. Why is the city now involved and why was the city not involved earlier?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 145
Registered: 02-2003
Posted on Wednesday, April 27, 2005 - 10:30 am:   

Mr. Thompson,

Here is a link to a response to a similar question about the city's involvement in 3537 and the Custer/3537 intersection in December.

http://message.ci.frisco.tx.us/scripts/show.pl?tpc=1&post=6318#POST6318

Please contact Frank Jaromin if you have additional questions.

fjaromin@friscotexas.gov
 

Ed Thompson
New member
Username: Ethompson

Post Number: 4
Registered: 11-2004
Posted on Thursday, April 28, 2005 - 01:41 pm:   

The linked thread says 4 months to complete and this thread says 6 months.

What has changed with the project to increase it by 50%?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 146
Registered: 02-2003
Posted on Thursday, April 28, 2005 - 04:05 pm:   

Mr. Thompson,

Per Frank Jaromin, City Engineer:

TxDot, Frisco and McKinney have expanded the scope of work for this project by adding right turn lanes, longer transitions and more construction phases of work to accomplish the construction.


Please contact Frank Jaromin if you have additional questions.

fjaromin@friscotexas.gov

 

Ed Thompson
New member
Username: Ethompson

Post Number: 5
Registered: 11-2004
Posted on Monday, June 27, 2005 - 08:17 am:   

What is the date for completion of the Main Street/Custer intersection improvements?
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 38
Registered: 10-2003
Posted on Tuesday, July 05, 2005 - 11:10 am:   

Mr. Thompson,

Construction on this project has begun and with the expanded scope of work, completion of the project is anticpated by January 2006.

If you have any additional questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Ed Thompson
New member
Username: Ethompson

Post Number: 6
Registered: 11-2004
Posted on Tuesday, September 13, 2005 - 10:33 am:   

What is the current date of completion for the Main Street/Custer intersection improvements?

Thanks.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 186
Registered: 02-2003
Posted on Wednesday, September 14, 2005 - 08:13 am:   

Mr. Thompson,

Per Hulon Webb, Senior Civil Engineer, "we are still anticipating completion in January 2006 contingent upon timely relocation of existing utilities."
 

Ed Thompson
New member
Username: Ethompson

Post Number: 7
Registered: 11-2004
Posted on Friday, November 18, 2005 - 08:31 am:   

Has this project completion been pushed back? What is the expected completion date?

(Message edited by admin on November 18, 2005)
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 64
Registered: 10-2003
Posted on Monday, November 21, 2005 - 04:29 pm:   

Mr. Thompson, thanks for the post. Unfortunately, unbeknownst to anyone a major concrete encased fiber duct run has been discovered to be in direct conflict with the proposed storm sewer trunk line.

Until such time as the fiber duct run can be relocated, the contractor will continue to work on completing the unaffected areas.

The estimated completion date for the project has been pushed back to early April.

If you have any additional questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Post as "Anonymous"
Enable HTML code in message
Automatically activate URLs in message
Action: