william
New member
Username: Tucker02

Post Number: 3
Registered: 03-2006
Posted on Friday, October 06, 2006 - 10:53 am:   

Are there any updates on widening Rolater by Liberty HighSchool.

(Message edited by admin on October 06, 2006)
 

Luke Jalbert, EIT
Moderator
Username: Luke_jalbert

Post Number: 4
Registered: 07-2006
Posted on Tuesday, October 10, 2006 - 10:53 am:   

This section of road is scheduled to start design near then end of this year. Design will take approximately 9 months to complete, with construction following in fall of 2007.
 

william
New member
Username: Tucker02

Post Number: 4
Registered: 03-2006
Posted on Tuesday, October 10, 2006 - 11:07 am:   

With the road not being expanded until after the Highschool opens, are there plans to put in a temporary stops signs for North/South Independance at Rolater and what about Rolater and where the HighSchool is. Thanks.
 

John
New member
Username: John

Post Number: 21
Registered: 01-2002
Posted on Tuesday, October 10, 2006 - 04:03 pm:   

Please clarify the section of Rolator to which you are referring. I understood that the Rolator Road construction between Coit & Independence is to begin as soon as Rodman finishes burying the new water main. Are you referring to Rolator between Independence & Custer?
 

Luke Jalbert, EIT
Moderator
Username: Luke_jalbert

Post Number: 5
Registered: 07-2006
Posted on Wednesday, October 11, 2006 - 03:37 pm:   

Rolater from Coit to Independence will begin construction as soon as the pipe is installed.

Rolater from Independence to Custer (by the above mentioned Liberty High School) will start construction in approximately 1 year.
 

Brian Moen, Transportation Manager
Moderator
Username: Brian

Post Number: 294
Registered: 07-2001
Posted on Wednesday, October 11, 2006 - 06:26 pm:   

William,

There will be a signal in place at Independence and Rolater when Liberty opens in 2007. This signal is being constructed as part of the widening of Independence that will be completed by August 2007.

At this time, signals are not planned for any of the intersections on Rolater in front of the school. We have discussed the possibility of one at Valley Brook and Rolater. However, this will be dependent on the location meeting warrants and having funding available.

We are also in the process of conducting warrant studies for Rolater and Custer. We are working towards having a signal in place at that intersection when school begins in August 2007.

Thanks
Brian Moen
Transportation Manager
 

william
New member
Username: Tucker02

Post Number: 5
Registered: 03-2006
Posted on Thursday, March 22, 2007 - 11:48 am:   

What is the current time frame on the starting/completion of the widening of Rolater between Coit and Independance. Also, when will construction start on the widening of Independance from 121 to Rolater?
 

Luke Jalbert, EIT
Moderator
Username: Luke_jalbert

Post Number: 10
Registered: 07-2006
Posted on Tuesday, April 03, 2007 - 08:32 am:   

William,
Currently the Rolater project is on hold based on AT&T relocating a pole line down the Rolater Alignment. They are currently working on the relocations. Once AT&T is complete, a new 42" water line will be installed, this should take 2 months. As soon as the water line is in place, construction on the road will begin. It should take about 9 months to complete.

Independence is also being held up by utility relocations. As soon as coserve relocates there utilities, the contractor will start on that section of Independence.

Thanks

Luke Jalbert, P.E.
Engineering Services
 

william
New member
Username: Tucker02

Post Number: 6
Registered: 03-2006
Posted on Tuesday, September 11, 2007 - 10:27 am:   

Are there any updates on the construction of Rolater between Coit and Independence and what is the status on the expansion of Independence from 121 to Rolater. Thanks.
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 78
Registered: 06-2003
Posted on Friday, September 14, 2007 - 03:23 pm:   

The roadway is 95% designed. The project is anticipate the bid by the end of this month. The project should be awarded for to the contractor in October and construction should start approximately 1-2 months later. The total time of construction is anticipated to be 6 months.
 

Marcus-Alan Gilbert
New member
Username: Marcalgi

Post Number: 1
Registered: 12-2007
Posted on Wednesday, December 19, 2007 - 11:39 am:   

Has the contract been awarded?
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 81
Registered: 06-2003
Posted on Thursday, December 27, 2007 - 03:05 pm:   

The project was awarded in October. Construction started on December 3rd. The contractor is Mario Sinacola who is currently surveying the project. The project is 270 calendar days. The Project Manager is Alyssa Sanders at 972-292-5438 if you have specific questions on the project.
 

william
New member
Username: Tucker02

Post Number: 7
Registered: 03-2006
Posted on Monday, February 25, 2008 - 08:37 am:   

What is the land on the South West corner of Rolater and Independence being cleared for? I looked for a commercial permit but wasnt able to find one.
 

Scott Ingalls, Zoning & Subdivision Admi
Moderator
Username: Scott_ingalls

Post Number: 437
Registered: 06-2003
Posted on Tuesday, February 26, 2008 - 09:54 am:   

William,

There are no approved plans or applications for the development of this corner.

Scott Ingalls
Zoning & Subdivision Administrator
 

John K
New member
Username: Johnk

Post Number: 1
Registered: 04-2008
Posted on Thursday, April 03, 2008 - 12:14 am:   

What is the current status of Rolater between Coit and Independence? Its now April 2008 and things seem to have been stalled for a while. It looks as though only about 500 feet of roadway from independence toward coit is complete with little to no progress beyond that.

Also whats happening with Independence between Rolater and Main. The west lane seems to be stuck in limbo.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 523
Registered: 02-2003
Posted on Friday, April 04, 2008 - 09:37 am:   

The Engineering Department provides a monthly status report of all projects they are responsible for or tracking. The April update was just posted and provides current status of projects. You can view the Engineering Department monthly update on the city's web site here:

http://www.friscotexas.gov/Departments/engineering/index.aspx?id=2027

Once on this page, click on "Monthly Staff Report"

City managed road projects listed in alphabetical order begin on page 8. You will find updates on both Independence and Rolater.
 

Edward Alan Wilson
New member
Username: Kanda4

Post Number: 4
Registered: 06-2011
Posted on Friday, July 01, 2011 - 06:44 pm:   

Does the city intend to plant any trees in the new median on Rolater between Independence and Custer. There were an awful lot of trees cut down for purposes of widening the road.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 87
Registered: 06-2008
Posted on Wednesday, July 06, 2011 - 08:36 am:   

Trees are included as part of the construction project on Rolater between Independence and Custer.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: