Eldorado Parkway Expansion Log Out | Topics | Search
Moderators | Register | Edit Profile

City of Frisco Question and Answer Board » Frisco Q & A » Eldorado Parkway Expansion « Previous Next »

  Thread Last Poster Posts Pages Last Post
  Start New Thread        

Author Message
 

Amy Ferguson
New member
Username: Amy_f

Post Number: 1
Registered: 07-2005
Posted on Friday, July 15, 2005 - 10:10 am:   

Saw earlier posting that Eldorado Parkway will become 6 lanes with construction slated to begin in early 2006. Was wondering about a few things such as the configuration of the roadway, proximity to current fences separating the road from existing subdivisions along Eldorado, and if a median is planned. Heard the roadway may be dug down below the current road on either side... any truth to that?
 

Amy Gill, Assistant to the City Manager
Moderator
Username: Amyg

Post Number: 96
Registered: 08-2002
Posted on Tuesday, July 26, 2005 - 10:18 am:   

The Eldorado Parkway Widening Project is scheduled to begin construction in early 2006. This construction is estimated to be completed by the end of 2007. The project will widen the existing 2-lane asphalt road to the proposed conditions of a 6-lane concrete divided roadway (with a median). The project limits are FM 423 and the DNT. Right turn/deceleration lanes will be constructed at most cross-streets. Median openings with left turn/deceleration lanes will be constructed at various locations along the project’s length. This median will vary along the project’s length as well, from 16’ planted to 5’ concrete. The following intersections with Eldorado Parkway will be widened and signalized: FM 423, Teel, Legacy, and the DNT. The average distance between the existing subdivision fences and the proposed curb of Eldorado is approximately 30’. The project will reconstruct to roadway at approximately the same grade at which it currently exists; “the roadway will” not “be dug down below the current road on either side”. For additional information, please contact Hulon Webb at the City of Frisco Engineering Services Department, (972) 335-5585.

Amy J. Baker, E.I.T.
City of Frisco, Engineering Services Department
6990 Main Street
Frisco, Texas 75034
(972) 335-5585 ext. 124



 

Anonymous
New member
Username: None

Post Number: 27
Registered: 11-2003
Posted on Wednesday, July 27, 2005 - 07:43 am:   

If the construction is supposed to start early next year then why was a layer of gravel and tar laid down on the road surface on Sunday? This seems to be a waste of taxpayer money when it is just going to get all torn up in 6 months.
 

Raj Sankar
New member
Username: Rsankar

Post Number: 1
Registered: 03-2006
Posted on Tuesday, March 21, 2006 - 12:24 am:   

I am planning to buy the house at Grayhawk subdivision the only neighborhood with out brick wall fence. My question would be, Is there a possibilty for a wall(fence) to reduce the noise level when Eldorado Parkway expands? Who will build it?
 

Scott Ingalls, Zoning & Subdivision Admi
Moderator
Username: Scott_ingalls

Post Number: 217
Registered: 06-2003
Posted on Tuesday, March 21, 2006 - 02:03 pm:   

Raj,

The developer of Grayhawk chose to not construct a masonry wall but to instead use landscaping to create a buffer. The only way for a wall to be constructed is by the developer or the HOA. The City of Frisco does not construct screening walls. The developer or HOA would be responsible for any construction costs. If you have any questions please feel free to contact me at 972.335.5580, ext. 157. Thank you.

Scott Ingalls
Zoning & Subdivision Administrator
 

Randy Allen
New member
Username: Texallen01

Post Number: 2
Registered: 03-2006
Posted on Tuesday, March 21, 2006 - 06:51 pm:   

Whats the timetable for widening Eldorado between Preston and the DNT?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 183
Registered: 07-2003
Posted on Wednesday, March 22, 2006 - 10:16 am:   

Staff is preparing an engineering contract to go to City Council in late April or early May for the design of Eldorado Parkway from Preston to Toll Road. We will be designing this in two phases one is Preston to North County to accelerate the process. We anticipate the engineering to take about 8 months and construction to start two months later and last about 9 months.

If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

Randy Allen
New member
Username: Texallen01

Post Number: 3
Registered: 03-2006
Posted on Wednesday, March 22, 2006 - 10:47 am:   

Thanks for the reply!

A few more quick questions:

What about the new Eldorado bridge over the train tracks. Will it have to be widened? If so, why wasn't this constructed wider to begin with?

 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 184
Registered: 07-2003
Posted on Friday, March 24, 2006 - 12:31 pm:   

The cost of the Eldorado Bridge project was 4 million dollars, to add the other bridge (three lanes) would be 1.5 to 2 million dollars extra. This money was used to construct other needed roads that are currently being used in the city. The Engineering staff performs traffic counts on most of the major roadways and continually views these numbers to help decide future road projects.
Frank Jaromin
972-335-5585 ext 129
 

Laura Uldrich
New member
Username: Mluldrich

Post Number: 1
Registered: 05-2007
Posted on Saturday, August 25, 2007 - 10:25 am:   

I just read in the Engineering Services Staff report from August 8, 2007 that TXDOT has revised the start date for the expansion of Eldorado from 423 to the Tollway to mid-2008 due to utility relocation? What is taking so long for the utility companies to complete this? It seems like the start date for this project keeps getting pushed out and pushed out, while the residents and commuters along Eldorado are the ones suffering. Any way to motivate the utility companies and TXDOT to get the project started?
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 74
Registered: 06-2003
Posted on Monday, August 27, 2007 - 10:32 am:   

The City is in the process of completing the acquisition of the right of way. The City could not begin right of way acquisition until the environmental assessment was obtained. This took 6 years to obtain due to the federal and state requirements. Once the right of way is acquired, the utilities will be relocated. Due to the delays in this TxDOT project, the City has proceeded with accelerated the design and construction of Panther Creek Parkway and the missing segment of Legacy to Panther Creek. This roadways will be completed by late next summer and provide an alternative route to Eldorado.
 

J Radcliffe
New member
Username: Spyder

Post Number: 6
Registered: 01-2006
Posted on Monday, August 27, 2007 - 12:36 pm:   

Any update on the Preston to Tollway expansion of ElDorado Parkway. According to the March 2006 pasted below, this should have begun this spring.

Posted on Wednesday, March 22, 2006 - 10:16 am: Staff is preparing an engineering contract to go to City Council in late April or early May for the design of Eldorado Parkway from Preston to Toll Road. We will be designing this in two phases one is Preston to North County to accelerate the process. We anticipate the engineering to take about 8 months and construction to start two months later and last about 9 months.
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 76
Registered: 06-2003
Posted on Tuesday, September 04, 2007 - 12:52 pm:   

Eldorado Parkway (DNT – Preston) City Council awarded the design contract to Wier & Associates on June 6, 2006, for the design of the westbound (northern) two lanes, including the westbound bridge over the BNSF Railway. Staff has received the ROW documents for acquisition. An agreement with BNSF to permit a railroad crossing is being developed, and the project will be bid when the permit is received. This project is expected to bid by the end of 2007 and should require 15-18 months to complete.
 

kat graham
New member
Username: Kat_graham

Post Number: 7
Registered: 03-2005
Posted on Monday, August 27, 2007 - 10:47 am:   

Why does the city continue to allow building permits for housing along Eldorado between 423 and Tollway? Obviously for the tax revenue. Eldorado traffic is making the quality of life poor in this area. I know you have stated Panther Creek is being developed quickly to help ease the traffic on Eldorado, but if you continue to allow houses to be built it doesn't prove anything. Why won't the city slow down the housing growth along Eldorado until the stae actually starts work on the road?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 455
Registered: 02-2003
Posted on Tuesday, September 04, 2007 - 04:23 pm:   

Per John Lettelleir, Director of Planning and Development:

Your question is one of the most commonly asked questions. The answer has two parts on why the City cannot withhold permits, and if we could, why the impact would be minimal.

1. The section of Eldorado Parkway between the Dallas North Tollway and FM 423 is a TXDOT roadway. The City cannot legally withhold building permits in this case because Eldorado Parkway is neither under the City’s control or the developer(s) control.

2. Other cities and developments in unincorporated areas of the county continue to issue building permits and those developments inevitably add traffic to our streets.

Traffic congestion in this part of the City has been one of City Council’s top priorities for the past few years, and City staff have been working with the other entities, especially TXDOT, to improve Eldorado Parkway sooner than later. Since Eldorado Parkway is not happening sooner, the City Council has taken the initiative to build Panther Creek Parkway over to DNT. Panther Creek Parkway is a City road. You may be thinking why Panther Creek Parkway was not started sooner, and the answer is that we all of the understanding that Eldorado Parkway would be constructed sooner.
 

Tracy Serio
New member
Username: Tserio

Post Number: 11
Registered: 08-2006
Posted on Friday, September 14, 2007 - 02:08 pm:   

How long to you think it will take to extend Panther Creek?

Thank you for starting this project early, it will be a big help in the end.
 

Elizabeth Metting, City Engineer/AsstDir
Moderator
Username: Elizabeth_metting

Post Number: 6
Registered: 07-2007
Posted on Wednesday, September 19, 2007 - 12:48 am:   

Panther Creek Parkway from Teel to the DNT is currently being designed as quickly as possible. Surveying and engineering design started in mid-May and plans are nearly complete. We must first acquire the property for the road, and negotiations have already begun. We are also researching ways to expedite the completion of construction with the goal to complete and open the road no later than the end of summer 2008. This project is a priority of the City Council, and should provide significant relief to the traffic issues in that area when completed.
 

Mike
New member
Username: Newyork1

Post Number: 5
Registered: 07-2007
Posted on Wednesday, September 19, 2007 - 10:14 pm:   

Will Panther Creek be six or four lanes wide? And also, are plans still on track to begin construction on the widening of Legacy between Lebanon and Warren from 4 to 6 lanes in early 2008?
 

Bryan Fritchie
New member
Username: Hogcall

Post Number: 17
Registered: 06-2006
Posted on Thursday, September 20, 2007 - 09:39 am:   

What about Panther Creek from Preston to DNT? Is that anywhere in the plans?
 

Elizabeth Metting, City Engineer/AsstDir
Moderator
Username: Elizabeth_metting

Post Number: 7
Registered: 07-2007
Posted on Thursday, September 20, 2007 - 11:14 pm:   

Mike:

Panther Creek is being designed as a four lane arterial.

Legacy plans are being designed and right now the schedule calls for construction during early-to-mid 2008.

(Message edited by admin on September 28, 2007)
 

Elizabeth Metting, City Engineer/AsstDir
Moderator
Username: Elizabeth_metting

Post Number: 8
Registered: 07-2007
Posted on Wednesday, September 26, 2007 - 11:45 pm:   

Bryan:

Panther Creek from Preston to DNT does not yet have a specified timeframe. There is a bridge over Panther Creek that will have to be built which adds to the project cost.

(Message edited by admin on September 28, 2007)
 

Damon Hammis
New member
Username: Dhammis

Post Number: 8
Registered: 09-2006
Posted on Thursday, September 27, 2007 - 03:38 pm:   

There was an article in the Dallas Morning News saying that TxDOT is nearly out of funds and are cancelling a lot of projects that haven't been contracted yet. Has the city been informed if the Preston Road, Eldorado Parkway or FM 423 projects are affected by this?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 460
Registered: 02-2003
Posted on Friday, September 28, 2007 - 08:53 am:   

Per Cissy Sylo, Director of Engineering:

None of the City’s projects should be affected by TxDOT’s announcement. The Article in the paper states that “The impact will be less severe in North Texas, where local officials are counting on more than $3 billion in upfront payments from the North Texas Tollway Authority as part of its deal to build the State Highway 121 toll road.” Eldorado & FM 423 are part of this $3B funding. Preston already is funded with gasoline sales tax dollars that were previously committed. Therefore none of the projects you mentioned are in jeopardy of being cancelled.
 

Adam Wallace
New member
Username: Enoughalready

Post Number: 1
Registered: 12-2007
Posted on Wednesday, December 05, 2007 - 08:35 pm:   

Are there plans to have 24 hour crews? I would think that if you asked residents in the area they'd be willing to put up with the noise for a short period if it means being done in 33% of the time.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 477
Registered: 02-2003
Posted on Thursday, December 06, 2007 - 09:39 am:   

Per Cissy Sylo, Director of Engineering:

Adam,

You asked if TxDOT was planning on worked 24 hours a day on the Eldorado construction project. TxDOT does not plan to have 24 hour crews working on the Eldorado construction. Very few construction projects in the United State have this type of work due to the safety of the workers primary. This is very dangerous for the workers. There are more fatalities in this type of construction zones than any other. Also the type of intensive lighting needed along the residential area, noise complaints anticipated, limited visibility for the workers to construct a quality product, and other construction difficulties make it difficult to work under these conditions.
 

Carolyn
New member
Username: Carolyn_k

Post Number: 7
Registered: 06-2006
Posted on Thursday, February 14, 2008 - 08:55 pm:   

I was just wondering what the status is on the El Dorado project. I see they having been installing/moving new telephone/utility poles, which I interpert as progress. Has the job been put out for bids? What is the estimated start date?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 501
Registered: 02-2003
Posted on Monday, February 18, 2008 - 01:35 pm:   

The project was bid on February 7, 2008 by TxDOT. The apparent low bidder is W.W. Webber, LLC. The amount of the bid was $21, 211,560.36. Currently TxDOT has a “delayed” construction start scheduled on the project since all the franchised utilities are not finished with their relocations until June 2008.
 

Larry Fravel
New member
Username: Larry

Post Number: 1
Registered: 04-2008
Posted on Tuesday, April 08, 2008 - 10:04 pm:   

First Question - are completion of northbound lanes for Teel at the El Dorado Pkwy intersection part or planned prior to, or part of the El Dorado widening?

Second Question- With the current anticipated Summer/early fall 2008 opening of Panther Creek btw Teel and DNT, has the city considered closing El Dorado during construction btw Teel and Legacy to accelerate the completion date for El Dorado?
 

Elizabeth Metting, City Engineer/AsstDir
Moderator
Username: Elizabeth_metting

Post Number: 11
Registered: 07-2007
Posted on Monday, April 14, 2008 - 11:19 am:   

1. Construction of the northbound lanes of Teel are a City responsibility, while the construction of FM 2934 (Eldorado) from FM423 to the DNT is a TxDOT project. The City is considering how best to provide the additional lanes in the appropriate timeframe so that when FM2934 is completed, Teel will also have 2 lanes in each direction north of Eldorado.
2. Since this project is under TxDOT's jurisdiction, the decision on whether to close FM2934 during construction is not a choice that can be made by the City. The City has discussed with TxDOT whether such a step would be feasible and if it would truly expedite the project. A complete closure would affect many residents, businesses, and the middle school, as well as the City's ability to provide for public safety. The decision from TxDOT and City staff members is that completely closing a portion of the road is not helpful to the project or the public.
 

Carl Babovec
New member
Username: Carlbob

Post Number: 1
Registered: 06-2008
Posted on Sunday, June 22, 2008 - 01:56 am:   

Are the electrical poles now going up in front of Eldorado Fairways temporary for the Eldorado (2934) expansion?

Why would the lines not be buried?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 548
Registered: 02-2003
Posted on Wednesday, June 25, 2008 - 07:53 am:   

Unfortunately, the bottom line is that the electric and cable utilities are unwilling to pay the additional costs of burying their utility lines. Additionally, there has been recent legal action by utility companies against cities that have passed ordinances requiring the lines to be buried. Once such example is where Oncor Electric Delivery took the City of Allen and a Coalition of Cities before the Public Utility Commission (“PUC”) to challenge their ability to require the lines to be buried. The Commission held that the cities could not place such requirement on the utility without the city (you the tax payer) paying the cost for burying such lines. This decision was challenged by Allen and the Coalition of Cities before Third District Court of Appeals and the court found in favor of the PUC upholding their ruling thus precluding cities from further blanket regulation of the burial of utilities.
 

Brandon Johnson
New member
Username: Brandonj71

Post Number: 1
Registered: 05-2008
Posted on Monday, June 23, 2008 - 11:19 pm:   

Almost July, and just wondering what is the latest update?... with so much new construction moving along at the NW and SW corners of ElDorado and DNT, those shopping centers are nearing completion and will bring in a substantially higher amount of traffic -- and we are still with a two-lane road to handle it all...
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 550
Registered: 02-2003
Posted on Wednesday, June 25, 2008 - 10:00 am:   

Each month the Engineering Services Department posts their monthly report online. Eldorado (FM2934) status can be found on page 7 of 13 and again on page 10 of 13 of this report. Here is a link to the report:

http://www.friscotexas.gov/uploadedFiles/Departments/engineering/reports/062008E nginineeringServicesFinalno%20shading.pdf
 

James Baker
New member
Username: Jzb54

Post Number: 1
Registered: 08-2008
Posted on Thursday, September 18, 2008 - 08:29 pm:   

Looks like the Engineering Services Department hasn't been posting their monthly reports since June. Anybody know why they don't have current info up?
 

Perry Harts, Senior IT Strategic Planner
Moderator
Username: Perry

Post Number: 42
Registered: 06-2002
Posted on Friday, September 19, 2008 - 08:20 am:   

The link above is for the June report. If you click on http://www.friscotexas.gov/departments/engineering/Documents/Monthly%20Report.pdf you will see a link to the current month.

Thanks for pointing that out.

(Message edited by perry on December 03, 2008)
 

Elizabeth Metting, City Engineer/AsstDir
Moderator
Username: Elizabeth_metting

Post Number: 17
Registered: 07-2007
Posted on Friday, September 19, 2008 - 01:53 pm:   

The specific links will always return you to that specific month's report. To get the current month at a future time, please go to the City's webpage, select Departments, then Engineering and then on the left hand side under "Extra Info" click Engineering, then Reports and then finally click on the main page "Monthly Staff Report".
 

Bryan Fritchie
New member
Username: Hogcall

Post Number: 30
Registered: 06-2006
Posted on Tuesday, December 02, 2008 - 05:13 pm:   

A right hand turn lane was added to the south bound DNT access road onto Eldorado. How come a right hand turn lane was not also added to the north bound DNT access road onto Eldorado? Surely there is more traffic traveling north to Eldorado than south to Eldorado.
 

Brian Moen, Asst. Dir. Eng. /Transp
New member
Username: Brian

Post Number: 1
Registered: 07-2001
Posted on Wednesday, December 03, 2008 - 06:50 pm:   

The right-turn lane on the southbound side was built by the development in the northwest corner of the intersection. There will be a right-turn lane added in the northbound direction as the southeast corner develops. If the right-turn lane has not been built with development by the time the Eldorado construction from DNT to Preston is ongoing in that area, we will construct the right-turn lane with the widening of Eldorado.

Thanks
Brian Moen
 

dean paulson
New member
Username: Nosluap57

Post Number: 2
Registered: 09-2007
Posted on Monday, April 13, 2009 - 04:33 pm:   

What plans are there, if any, to construct traffic signals on Eldorado to facilitate egress from the adjacent subdivisions?
 

Brian Moen, Asst. Dir. Eng. /Transp
Moderator
Username: Brian

Post Number: 332
Registered: 07-2001
Posted on Tuesday, April 14, 2009 - 06:21 pm:   

Dean,

The information below covers plans for two different sections of Eldorado. One is currently under construction and one section will begin construction shortly.

Eldorado - FM 423 to Dallas Parkway

There is a signal planned for the main driveway between the Target and Market Street developments. This will be constructed once the reconstruction of Eldorado is complete.

Locations that we have studied previously and will evaluate again after construction is complete are Eldorado at Grayhawk, and Eldorado at Lennox.

Eldorado - Dallas Parkway to Preston

This section is also being widened to 6 lanes as well. The construction of this section was awarded at the last Council meeting (April 7). It includes the construction of signals for Eldorado at Frisco Street, Eldorado at North County, and Eldorado at Rogers. We have had several questions as to why a signal is planned for Eldorado at Rogers. This location is needed due to sight distance restrictions.


Thanks
Brian
 

Scott Bowers
New member
Username: Scottb

Post Number: 1
Registered: 04-2009
Posted on Friday, April 24, 2009 - 11:47 pm:   

Two questions about the Eldorado project between the Tollway and 423:
1) Are sidewalks in front of North Ridge and Grayhawk included? The newly installed sod leaves no room for sidewalks, yet the new entrances to these subdivisions include sidewalks.

2) Why are there no right-side turning lanes into the entrances of the new subdivision on the north side between the Tollway and Teel? Is the subdivision responsible for them?
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 20
Registered: 06-2008
Posted on Tuesday, April 28, 2009 - 08:47 am:   

Scott,

Below are answers to your questions:
1) Sidewalks are not included in the current construction of Eldorado between the DNT and FM 423; however the City is planning on installing sidewalks when the roadway construction project is completed.

2) Right turn lanes will be included in at Lenox Lane and Briar Ridge Rd as part of the construction project.
 

Ravi Sharma
New member
Username: Ghawk

Post Number: 1
Registered: 08-2009
Posted on Wednesday, September 09, 2009 - 03:35 pm:   

I drive through Eldorado everyday and looks like the construction is almost done. Some more work remaining on the intersections (Teel/Eldorado, legacy/Eldorado). Today they were laying sod in the medians. Any update on completion date? Should be too far.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 26
Registered: 06-2008
Posted on Thursday, September 10, 2009 - 11:22 am:   

Construction of Eldorado between FM 423 and the Dallas North Tollway is nearing completion. The contractor is well ahead of schedule. We anticipate switching traffic to the new eastbound lanes in the next couple weeks and expect project completion in the next 2 to 3 months.
 

Scott Stedman
New member
Username: Texastek76

Post Number: 2
Registered: 12-2006
Posted on Tuesday, September 29, 2009 - 10:59 am:   

Is the speed limit on Eldorado really going to be 40 MPH or is that temporary until all construction is complete?
 

Joel Fitts, Senior Traffic Engineer
Moderator
Username: Joel_fitts

Post Number: 59
Registered: 03-2008
Posted on Thursday, October 01, 2009 - 06:26 pm:   

Scott,

Eldorado Parkway between FM 423 and the Dallas North Tollway is a state roadway and decisions regarding its construction and speed limits are made by TxDOT. Typically, speed limits on new roadways are determined based on speed studies that are conducted after construction is completed. In the case of a roadway that is widened, the process is a little more complicated as you go from what the speed limit was to what it needs to be (after a study can be conducted). This process includes an interim speed limit, which TxDOT has posted as 40mph in this case.

The City has made a request to TxDOT to retain the previous 45mph speed limit until the new speed study can be conducted. We are waiting for our request to go through TxDOT's approval process.

Regardless of what speed limit is posted right now, it could change once construction is complete and the new speed study is conducted.

Joel Fitts
Senior Traffic Engineer
 

Dam Hoang
New member
Username: Damhoang

Post Number: 3
Registered: 01-2005
Posted on Tuesday, October 06, 2009 - 01:34 pm:   

Is Eldorado Parkway going to get street lights like Main st. or Panther Creek?
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 28
Registered: 06-2008
Posted on Wednesday, October 07, 2009 - 08:05 am:   

Upon completion of the roadway construction by TxDOT, the City of Frisco is planning on installing lights in the median. We have begun engineering on the project and expect to go to construction early next year.
 

Don Tedlock
New member
Username: Dtedlock

Post Number: 1
Registered: 03-2012
Posted on Saturday, March 24, 2012 - 02:06 pm:   

I can't remember the thread; but I thought I read a few months ago that construction on Eldorado between Preston and Independence would begin January 2012. What is the status of widening Eldorado?
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 108
Registered: 06-2010
Posted on Tuesday, March 27, 2012 - 12:16 pm:   

The design for the Eldorado Parkway project is almost complete. We anticipate bidding out the project to contractors next month and construction is scheduled to start in June or July this year depending on the relocation of franchise utilities(i.e. Coserv Poles, ATT fiber, Timewarner Cable).
 

John Pinzone
New member
Username: Crownridge

Post Number: 2
Registered: 12-2012
Posted on Thursday, December 27, 2012 - 12:05 pm:   

What about Panther Creek from DNT to Preston? This area is growing sunstantially.
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 316
Registered: 06-2010
Posted on Wednesday, January 09, 2013 - 11:10 am:   

There are no immediate plans or funding for the extension of Panther Creek between DNT and Preston. This project will likely be considered and prioritized as part of a future bond package.
 

Jenny Dowdy
New member
Username: Iknowfrisco

Post Number: 1
Registered: 03-2015
Posted on Tuesday, March 24, 2015 - 10:41 am:   

Is there any further discussion extending Panther Creek from DNT to Preston? Thank you!
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 782
Registered: 06-2010
Posted on Thursday, April 09, 2015 - 02:23 pm:   

There are no immediate plans or funding for the extension of Panther Creek between DNT and Preston. This project will likely be considered and prioritized as part of a future bond package.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: