Jonathan Gordon
New member
Username: Scoobasteve2k1

Post Number: 1
Registered: 05-2008
Posted on Friday, May 30, 2008 - 07:16 am:   

When is Coit (between Main and Eldorado) going to be repaved / widened? It seems like filling potholes has turned into a daily occurence there now.

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 545
Registered: 02-2003
Posted on Tuesday, June 03, 2008 - 08:17 am:   

Coit Road from Main Street to Panther Creek Parkway was included in the 2007 Collin County Bond Program. At this time, we are waiting on Collin County to notify us when the funding will be available for the project. If funding is available, we are hoping to begin design this year, begin construction in Fall 2009 and complete the project in early 2011.

Jason Brodigan, P.E.
Senior Civil Engineer

City of Frisco, Engineering Services
George A. Purefoy Municipal Center
6101 Frisco Square Blvd., 3rd Floor
Frisco, Tx 75034

Direct: (972) 292-5434
Fax: (972) 292-5016

srinivas suri
New member
Username: Sris

Post Number: 1
Registered: 01-2010
Posted on Thursday, January 28, 2010 - 09:45 am:   

Any update on this?

Jason Brodigan, Sr. Civil Engineer
Username: Jason_brodigan

Post Number: 33
Registered: 06-2008
Posted on Tuesday, February 02, 2010 - 01:35 pm:   

Collin County has not yet been able to provide funds for this project; however, we have decided to move forward with the design. We are currently working with a consultant engineer to begin the design of the reconstruction of Coit Road to 4 lanes between Main St. and Eldorado Pkwy. The design should begin in April and be completed by the end of 2010. Again, dependent on availability of funding, we hope to begin construction in early 2011 and complete the project by the end of 2011.

Rob Brodner
New member
Username: Rbrodner

Post Number: 4
Registered: 11-2006
Posted on Thursday, February 18, 2010 - 01:17 pm:   

Will this only be paved/widened as far north as Eldorado Pkwy? I believe the project as specified to Collin County for the 2007 Transportation Bond was to take Coit all the way to Panther Creek Pkwy.

See item 07-23 Frisco: rojects/AllItems.aspx

Elizabeth Metting, City Engineer/AsstDir
Username: Elizabeth_metting

Post Number: 26
Registered: 07-2007
Posted on Sunday, February 21, 2010 - 10:10 pm:   

The first phase of the project will be to widen Coit to 4 lanes from Main Street to north of Eldorado Parkway. A second phase of the project will be needed to complete construction of the road to Panther Creek Parkway.

Add Your Message Here
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Options: Enable HTML code in message
Automatically activate URLs in message