Road Work Ahead signs Log Out | Topics | Search
Moderators | Register | Edit Profile

City of Frisco Question and Answer Board » Frisco Q & A » Road Work Ahead signs « Previous Next »

  Thread Last Poster Posts Pages Last Post
  Start New Thread        

Author Message
 

CAT_HERDER
New member
Username: Cat_herder

Post Number: 5
Registered: 02-2003
Posted on Thursday, December 13, 2007 - 01:20 pm:   

For over a week there have been "Road Work Ahead" signs in place at each end of Red Bud Drive in Red Bud Estates. So far I have seen no work being done. The same signs were placed twice before for about 1 week each time and nothing was done then either. What gives?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 482
Registered: 02-2003
Posted on Friday, December 14, 2007 - 02:10 pm:   

Per Brad Wooley, Streets Superintendent:

We have had work scheduled for approximately a week to crack seal at Red Bud Estates. We were not able to get started until today due to the wet weather. We will make sure to pick-up and re-set the signs on a daily basis as we can get the crack sealing done.

Brad Wooley
Street Superintendent
City of Frisco, Texas
972-292-5833

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: