Posted on Tuesday, November 05, 2013 - 11:56 am:   

It seems like construction has been halted on this section of road. Cones went up on end of August and now 2 months later they are still there.

Is there utility franchise disagreements again over this area. It seems from past research that the City has many delays over utility franchise disputes.

If that is the case here (and even if not) can you elaborate on why these disputes continue to arise and what the plan is to reduce these lengthy delays
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 127
Registered: 06-2008
Posted on Monday, November 25, 2013 - 08:22 am:   

Mr. Gallant,

It may appear at times that construction is halted, but work on the project has steadily continued. You may have noticed this week that traffic was switched onto the new pavement on Stonebrook. As of this week, we believe all utility conflicts are resolved and do not expect additional delays.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: