Sriram Iyer
New member
Username: Sriramiyer

Post Number: 3
Registered: 06-2005
Posted on Saturday, January 28, 2006 - 08:51 am:   

I noticed that some new water pipes are being put in on Eldorado east of Hillcrest. Does this project also include widening of the road in the same direction?
Also, as far as Coit is concerned, when do you think it will be extended to reach Eldorado?

Thanks
Sriram Iyer
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 177
Registered: 07-2003
Posted on Monday, January 30, 2006 - 08:51 am:   

The water line work you see on Eldorado is being installed by North Texas Municipal Water District. (NTMWD). The remaining east bound lanes of Eldorado and Coit Road from Main to Eldorado are scheduled in the 2006 bond package that will be going to the voters in May. If the Bond Package passís, this road will could be under construction in Late 2007.


If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Post as "Anonymous"
Enable HTML code in message
Automatically activate URLs in message
Action: