For tonight's Planning and Zoning meeting, a preliminary site plan for Roach Middle School is on the agenda. There is some sort of note on the plans referencing the construction of roadway improvements to Independence; however, the note is not legible. It appears it may state "Prop. Pavement by Others". Is this what the note states? By City Ordinances, developers must dedicate their half of the right-of-way, construct a minimum of 2 lanes of pavement, and other roadway improvements (water, drainage, street lighting, sidewalks, etc) when they develop their property. Are these improvements being constructed with this school? Will these required improvements be constructed prior to the school opening?

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 9
Registered: 02-2003
Posted on Thursday, April 15, 2004 - 09:11 am:   

Two lanes of Independence will be constructed by the opening of the school. The City is coordinating with FISD to get the two lanes built as required by the Subdivision Ordinance.

If you have any additional questions about this project, feel free to contact me at (972) 335-5540 ext 140.

John Lettelleir
Director of Planning

Add Your Message Here
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Options: Post as "Anonymous"
Enable HTML code in message
Automatically activate URLs in message