I have just been informed by a pool builder that any new pools starting after Feb 1, 2007 will be required to purchase water from a different source to fill the pool. Is this information correct?

Thanks in advance.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 353
Registered: 02-2003
Posted on Friday, January 12, 2007 - 03:04 pm:   

Per Gary Hartwell, Director of Public Works:

That information is incorrect. Public Works has established no such deadline. Pools can continue to be filled using City water. If you have any further questions, contact Gary Hartwell at 972-292-5800.
 

Pam Downey
New member
Username: Pdowney29

Post Number: 1
Registered: 08-2013
Posted on Wednesday, August 28, 2013 - 12:43 pm:   

My new pool is under construction. Do I need to do anything before starting to fill it? They say it will take 7 days to fill.
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 510
Registered: 06-2010
Posted on Friday, September 06, 2013 - 01:56 pm:   

No action is required.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: