Jim Williamson
New member
Username: Jimw

Post Number: 3
Registered: 04-2006
Posted on Monday, August 14, 2006 - 04:47 pm:   

Hello,

Will the Dallas North Tollway be opened in stages, or will the entire Gaylord - 380 be opened at once?
 

Mark Bouma
New member
Username: Mbouma

Post Number: 1
Registered: 08-2006
Posted on Monday, August 14, 2006 - 11:13 pm:   

The current plans are to open the entire length of the Dallas North Tollway (DNT) extension to US 380 at one time by September 2007. We will evaluate opportunities for staged openings, but no decisions have been made. Southbound staged openings may be feasible, but any staged opening in the northbound direction short of Eldorado may actually increase congestion. Gaylord is a two-lane exit currently (interim condition); none of the other ramps have the capacity to be open as two lanes.

Mark Bouma
Director of Engineering
North Texas Tollway Authority
 

Joe Wade
New member
Username: Joewade

Post Number: 5
Registered: 03-2005
Posted on Wednesday, November 01, 2006 - 07:58 pm:   

It appears that work on the service roads north of El Dorado is progressing well. Will the west service road be opening soon between El Dorado and 380?
 

Mark Bouma
New member
Username: Mbouma

Post Number: 2
Registered: 08-2006
Posted on Saturday, November 04, 2006 - 12:19 am:   

While most of the paving is complete for the west service road, several key items remain to be completed before traffic can be switched, including inlet construction, paving of the intersection at US 380, signal construction at US 380 and at Eldorado Parkway, and guardrail installation. The current schedule is to open the west service road (southbound Dallas Parkway) in the February to March 2007 timeframe.

Mark Bouma
Director of Engineering
North Texas Tollway Authority
 

Scott
New member
Username: Scott475

Post Number: 6
Registered: 10-2004
Posted on Thursday, February 22, 2007 - 01:24 pm:   

Are we still set for the service road opening up this month or next?
 

Mark Bouma
New member
Username: Mbouma

Post Number: 3
Registered: 08-2006
Posted on Friday, March 09, 2007 - 12:34 pm:   

We are working with our contractors to set a revised open to traffic date for the southbound service road. Completion of inter-agency reviews and agreements have contributed to delays in completing the work. Paving and signals remain to be installed at US 380 and Eldorado. Currently we anticipate the service road to open in May 2007.

Mark Bouma
Director of Engineering
North Texas Tollway Authority
 

Brian C
New member
Username: Brianc

Post Number: 99
Registered: 06-2003
Posted on Friday, March 09, 2007 - 10:32 pm:   

Mark,
The NTTA always has done a great job managing the construction schedule. However, why was the bridge at Warren and Lebabon both kept closed for so long instead of at least one being a priority.
 

Mark Bouma
New member
Username: Mbouma

Post Number: 4
Registered: 08-2006
Posted on Tuesday, March 20, 2007 - 10:25 am:   

The bridges at Warren and Lebanon are being constructed by different contractors and the schedules are not tied together. Originally, the Warren, Lebanon and Stonebrook bridges were all going to be built simultaneously. The cross streets were to be narrowed and each bridge built half at a time. Working with the City of Frisco, an alternate plan was instituted whereby first Stonebrook was closed for full bridge construction and then Lebanon was closed for construction. This was thought to provide the least disruption to Frisco residents and to Frisco High School. Since Warren traffic is much lower and Gaylord provides a nearby alternate route, Warren and Lebanon were not tied together.

Warren Parkway is scheduled to reopen by early May. At this time, items remaining are paving of u-turns, installation of permanent traffic signals and completion of median islands and striping. The u-turns on Warren will open a few weeks later after the bridge railings and u-turn guardrails are completed.

The bridge end supports are complete at Lebanon. The center support columns are currently being constructed and beams should be installed in April. The bridge is scheduled to be back open to traffic by July.

Mark Bouma
Director of Engineering
North Texas Tollway Authority
 

Joe Wade
New member
Username: Joewade

Post Number: 6
Registered: 03-2005
Posted on Saturday, April 07, 2007 - 10:35 am:   

regarding the service roads opening in May, there is no activity at this time for "Paving and signals remain to be installed at US 380 and Eldorado." so what is the deal?????

Thanks.
 

Scott D
New member
Username: Scottster

Post Number: 1
Registered: 05-2007
Posted on Saturday, May 19, 2007 - 05:47 am:   

We are nearing the end of May 07 and I was wondering if any new updates on ALL progress on unopened areas of the tollway could be released? If so could you please add as much detail as possible. PLEASE get those of us driving through town excited as the comute has been long and painful for all for a long LONG time!
 

Brian C
New member
Username: Brianc

Post Number: 111
Registered: 06-2003
Posted on Monday, May 21, 2007 - 06:11 pm:   

"Warren Parkway is scheduled to reopen by early May."

Works have been working on Warren 8 of the last 45 days. A few days it rained. Is there an updated schedule and reason for the lack of progress?
 

Mark Bouma
New member
Username: Mbouma

Post Number: 5
Registered: 08-2006
Posted on Thursday, May 31, 2007 - 10:30 pm:   

Two weeks ago our contractors stated that the new southbound frontage road from US 380 to Main Street would be open by July 2nd. Unfortunately, it has rained most days since then, but we are still going to do everything possible to open the roadway by that date. The contractor chose to hold off starting the intersection work until all the signal equipment was available and other coordination was in place since TxDOT stipulated that the construction on US 380 can not exceed 60 days.

Warren Parkway is in its final stages of work. The subcontractor that will slip the rail on the bridge has mobilized on site this week. We anticipate the remainder of the bridge will open in June.

The first bridge deck pour for Lebanon is scheduled for either June 1 or June 4, pending weather. Bridge work will continue through June and we still anticipate the bridge to be opened in July.

The DNT main lanes are still scheduled to open in September 2007 from SH 121 all the way to the new terminus south of US 380.

While signs are going up between Gaylord and future John Hickman and it looks like this section is almost complete, it will not be feasible to open this short segment early. The next toll plaza ramps north are still under construction and will not be substantially complete until the end of August. Additionally opening this short segment could cause greater congestion, especially in the northbound direction, since it is only a single lane ramp without the capacity the two lane ramp exit at Gaylord provides.

Thanks

Mark A. Bouma, P.E.
Director of Engineering
North Texas Tollway Authority
 

Diego Rodriguez
New member
Username: Dar1474

Post Number: 1
Registered: 07-2007
Posted on Tuesday, July 03, 2007 - 11:32 am:   

Any update on the opening of the new southbound service road lanes? Also, is the Sept. opening of the mainlanes going to be affected by all this rain????
 

Mark Bouma
New member
Username: Mbouma

Post Number: 6
Registered: 08-2006
Posted on Sunday, July 08, 2007 - 05:14 pm:   

The rains have severely hampered our contractor's ability to complete the southbound service road connection to US 380. In order to construct a proper roadbed for the intersection, it has to be dug out about 3-1/2' - this is below the ditch line, so every time it rains, the contractor loses several days waiting for the ground to dry up. The lastest estimate we have is to complete and open this section by the end of July, provided the weather cooperates.

The NTTA is still committed to opening the main lanes in September. It will probably be late in the month.

Mark A. Bouma, P.E.
Director of Engineering
North Texas Tollway Authority
 

Charles H Elliott
New member
Username: Cncaggies

Post Number: 2
Registered: 03-2006
Posted on Monday, July 23, 2007 - 09:44 am:   

Mark Bouma mentioned in a post on May 31 above that the bridge at Lebanon would be opening in July. Seeing as we only have about a week, is that work going to be finished on time?
 

Diego Rodriguez
New member
Username: Dar1474

Post Number: 2
Registered: 07-2007
Posted on Friday, August 03, 2007 - 08:44 am:   

I noticed that at HGWY 380 and the DNT the barriers have been removed, the intersection is paved, and the poles for the traffic signals have been installed. Is there an opening date for the new service road????
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 438
Registered: 02-2003
Posted on Friday, August 03, 2007 - 03:23 pm:   

The new Southbound Dallas Parkway service road from US 380 to Eldorado is scheduled to open on Sunday, August 5th. Crews will begin work at 8am on Sunday and the new lanes are expected to open early Sunday afternoon. Motorists are advised to use caution in the area as they adjust to the new traffic patterns. Motorists are also advised to take note of significant changes to the traffic signal operations at US 380/Dallas Parkway and Eldorado/Dallas Parkway.


Brian A. Moen, P.E.
Assistant Director of Engineering Services/Transportation
City of Frisco
6101 Frisco Square Boulevard, Third Floor
Frisco, Texas 75034
Phone (direct): 972-292-5450
Phone (department) 972-292-5400
Fax: 972-292-5016
E-mail: bmoen@friscotexas.gov
Web Page: www.friscotexas.gov
 

Mike
New member
Username: Newyork1

Post Number: 3
Registered: 07-2007
Posted on Sunday, August 05, 2007 - 10:36 pm:   

Are plans still intact to open the tollway in September?
 

Mark Bouma
New member
Username: Mbouma

Post Number: 7
Registered: 08-2006
Posted on Tuesday, August 07, 2007 - 10:11 am:   

The Dallas North Tollway extension is scheduled to open from SH 121 to US 380 at the end of September 2007. The current plan is to open on Friday afternoon, September 28.

The Lebanon bridge over the Tollway will be opened to traffic before school starts on August 27th.

Mark A. Bouma, P.E.
Director of Engineering
North Texas Tollway Authority
 

Barry Chassie
New member
Username: Tincup611

Post Number: 6
Registered: 01-2007
Posted on Tuesday, August 07, 2007 - 01:36 pm:   

Is there any reason why there is not a right turn lane on east bound Eldorado to turn Southbound on Dallas Parkway or a left turn lane coming the other way? There is plenty of room there for them. You still get backed up in traffic if 1 car doesn't turn right at the light.
thanks
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 440
Registered: 02-2003
Posted on Wednesday, August 08, 2007 - 08:04 am:   

NTTA opened the southbound frontage road from SH380 to Main Street last Sunday. The City of Frisco assisted with adjustments to the traffic signals on Dallas Parkway at US380 and Eldorado Parkway.

A sub-contractor on the project is scheduled to stripe the new pavement on Eldorado at the interchange this Thursday which will include additional lanes Eldorado Parkway and the frontage roads.

Projects like this have to be staged to accommodate traffic movements during the construction. Therefore, it was necessary to open the SB frontage road and leave single lane approaches on Eldorado Parkway to accommodate the striping work this week.

John Black
Sr. Traffic Engineer

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: