Brian C
New member
Username: Brianc

Post Number: 29
Registered: 06-2003
Posted on Tuesday, February 08, 2005 - 04:15 pm:   

City staff has approved that Coit be started ASAP. Has the city made an offer for the remaining ROW? Can you also tell us the current status of this project or expected timelines? Thanks.


(Message edited by admin on February 09, 2005)
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 130
Registered: 07-2003
Posted on Wednesday, February 09, 2005 - 11:00 am:   

Prior to the City making an offer we need to do some preliminary engineering to find out what we need for ROW and slope easements. Once this is complete the property has to be appraised because the City has to follow the guide lines set by the State on these matters. We have started the appraisal phase this week and hope to have that in hand in 4 – 6 weeks.


If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

R. Todd Koele
New member
Username: Tkoele

Post Number: 7
Registered: 06-2004
Posted on Wednesday, February 09, 2005 - 02:04 pm:   

For this phase of Coit road construction is the intention to have 2 lanes in each direction from 121 to Main?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 131
Registered: 07-2003
Posted on Wednesday, February 09, 2005 - 04:28 pm:   

The intent of this phase of construction is to have 2 lanes in both directions from Main to SH 121 and left turn lanes. We are looking at constructing Rolator west of Coit and partial to the east.
 

Brian C
New member
Username: Brianc

Post Number: 33
Registered: 06-2003
Posted on Monday, February 28, 2005 - 11:10 am:   

Has there been a status update on the appraisal? Is this the state, outside agency, etc. that does the appraisal? Does staff get status updates on the progress?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 141
Registered: 07-2003
Posted on Monday, February 28, 2005 - 01:46 pm:   

The next status report will be make to City Council. I am sorry I can not provide any further information. There is no State agency involved in this process.


If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 52
Registered: 06-2003
Posted on Friday, March 04, 2005 - 06:06 pm:   

Engineering is being done by RLK Engineering anticipated to be complete in April 2005. Right of way exhibits have been forwarded to the appraisal company. Once right of way is acquired, utilities will begin and are expected to take 6 weeks to complete. Construction is anticipated to being in June 2005 (dependent on ROW and utilities) and be complete in early 2006.

 

Brian C
New member
Username: Brianc

Post Number: 36
Registered: 06-2003
Posted on Thursday, March 31, 2005 - 04:06 pm:   

There was a 3/21 deadline for Lawler to decide on the offer? What happened. If ED is going to be needed.. is that immediate or a court process?

Thanks
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 132
Registered: 02-2003
Posted on Monday, April 04, 2005 - 09:35 am:   

Per Scott Young, Asst. City Manager:

The official requisite for a formal offer and response has passed. However, the City is continuing to try and reach a solution with Mr. Lawler, with continued meetings and dialogue. If we are unable to reach an agreement, then the city will move forward with condemnation. The condemnation process starts with the city filing a petition at the court. The court will then appoint 3 special commissioners who will hold a special commissioners hearing. At that hearing the commissioners will hear testimony regarding the fair market value of the property and will set a value to be awarded to the landowner. Once the city puts up the money with the court, then the city can take possession of the land. Either side if they don't agree with the value of the special commissioners can appeal that decision, it will then go back to the court for a full trial.

this is an abbreviated description of the process.
 

Brian C
New member
Username: Brianc

Post Number: 40
Registered: 06-2003
Posted on Wednesday, May 11, 2005 - 12:08 pm:   

What is the latest news on Coit?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 156
Registered: 07-2003
Posted on Thursday, May 12, 2005 - 01:47 pm:   

A total of seven (7) bids were opened on May 5, 2005, at 2:05 p.m. with Mario Sinacola & Sons Excavating, Inc., being the low bidder at $4,421,682.38. The engineer’s opinion of probable cost was $4,685,797.00.

Sinacola’s base bid was $3,820,552.89 and the engineer’s opinion of probable cost of the base bid was $3,972,767.00. Alternate 1 accounts for median irrigation. Sinacola’s Alternate 1 bid was $166,373.56 and the engineer’s opinion of probable cost of Alternate 1 was $221,585.00. Alternate 2 accounts for median lighting. Sinacola’s Alternate 2 bid was $434,755.93 and the engineer’s opinion of probable cost of Alternate 2 was $491,445.00. Staff is recommending that both Alternates be included in the Agreement in addition to the base bid.

Coit Road has two phases one is to build Coit north of College to help the traffic at the high school and the rest is in phase two.

If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

Brian C
New member
Username: Brianc

Post Number: 41
Registered: 06-2003
Posted on Friday, May 13, 2005 - 02:18 am:   

Thanks. Does this imply ROW is settled for all tracts that were needed. Either way, is there a projected start and finish date for these two phases.
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 157
Registered: 07-2003
Posted on Friday, May 13, 2005 - 03:03 pm:   

No, the ROW has not been settled so I can not provide a start date on phase 2. Phase 1 is currently going to the next City Council meeting for approval. Phase 1 is expected to start late June or ealy July.
If you have further questions please call me at 972-335-5585 ext 129
Frank Jaromin
 

Paula Ogden
New member
Username: My3sons

Post Number: 2
Registered: 04-2005
Posted on Monday, July 18, 2005 - 04:09 pm:   

Has the ROW been settled yet for Coit south of College? What is the scheduled completion date for phase 1?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 165
Registered: 07-2003
Posted on Wednesday, July 20, 2005 - 09:46 am:   

Yes, the City has taken the ROW and is in the process of relocating the utilities. Phase I is progressing and paving is scheduled to start the week of July 25 if no other delays occur. The contract time on this project for phase I is to be complete prior to opening of school but due to utility relocations (SBC and Coserv) we anticipate this part of Coit to open late August or early September. Staff and the Mario Sinacola is trying to make time up in every way possible to have this important roadway open.

If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

Brian C
New member
Username: Brianc

Post Number: 45
Registered: 06-2003
Posted on Monday, July 25, 2005 - 12:34 pm:   

What is the schudule for Phase 2 now that ROW is not an issue. I believe council has already approved funding.
 

Brian C
New member
Username: Brianc

Post Number: 48
Registered: 06-2003
Posted on Friday, August 19, 2005 - 01:20 am:   

following up.. is Phase 2 going to start/continue now?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 167
Registered: 07-2003
Posted on Friday, August 19, 2005 - 11:26 am:   

The current plan is to have Coit Phase II complete in late January 2006, however there will be time extensions related to utilities not relocating in time. The contractor is continuing to work were possible.


If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

Paula O.
New member
Username: My3sons

Post Number: 3
Registered: 04-2005
Posted on Monday, September 12, 2005 - 12:24 pm:   

Will there be a sidewalk installed along Coit between Shepherd's Hill and Centennial High School? Thanks in advance.

(Message edited by admin on September 13, 2005)
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 53
Registered: 10-2003
Posted on Tuesday, September 13, 2005 - 06:07 pm:   

Thanks Paula for the post. The current Coit Road project will include a sidewalk from the high school site, extending approximately 1100 feet north on the west side of Coit, where it will tie in to the existing sidewalk. This will provide a continous sidewalk from the High School to Sheperds Hill. It is anticipated to be complete no later than February 2006, with the next phase of construction.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Brian C
New member
Username: Brianc

Post Number: 51
Registered: 06-2003
Posted on Wednesday, October 05, 2005 - 10:56 am:   

1. There does not seem to be any work in progress. Have unexpected issues been found?



(Message edited by admin on October 06, 2005)
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 55
Registered: 10-2003
Posted on Thursday, October 06, 2005 - 11:20 am:   

Thanks Brian for the post. There have been no unexpected issues found. In fact if drive Coit north of Rolater today you will see that the sidewalk construction has already begun. At this rate the contractor should have no problem completing the sidewalk ahead of schedule.

As for the construction of Phase 2, there is substantial work in progress. Trees have been removed and grading is commencing from Lebanon to College.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Jon Bryant
New member
Username: Jon_bryant

Post Number: 2
Registered: 09-2005
Posted on Thursday, October 06, 2005 - 02:12 pm:   

I have noticed all of the trees that were dug up alongside northbound Coit. Could there not have been a plan to have those trees relocated to developing neighborhoods in the area, like the Shepard Hills area? Perhaps a notice to citizens "Hey, we're digging up trees... $100 bucks and we'll replant it in your backyard?".

It just seems as though that's a big waste of trees when that's exactly what we need more of.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 197
Registered: 02-2003
Posted on Monday, October 10, 2005 - 08:42 am:   

The trees removed from the Right-of-Way along Coit Road were all Hackberry trees. Hackberry trees are specifically excluded from being 'protected' trees per the City's Tree Ordinance.
 

David R. Smith
New member
Username: Fegary

Post Number: 9
Registered: 02-2003
Posted on Monday, October 10, 2005 - 01:07 pm:   

Which ordinance lists the "protected trees" and can you provide a link to it?

(Message edited by admin on October 11, 2005)
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 199
Registered: 02-2003
Posted on Tuesday, October 11, 2005 - 04:35 pm:   

Here is a link to the Tree Ordinance:

http://www.friscotexas.gov/uploadedfiles/Departments/Planning_Development/Comp_z oning_ord_92701/Article_IV/Section_03.pdf
 

Paul Konen
New member
Username: Pkonen

Post Number: 6
Registered: 03-2003
Posted on Friday, October 14, 2005 - 11:55 am:   

When the new section of Coit is completed between College and Lebanon, will the "old" section be rebuilt? There are a lot of pavement failures occuring along this stretch.
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 58
Registered: 10-2003
Posted on Friday, October 14, 2005 - 03:30 pm:   

Thanks Paul for the post. Yes, sections of existing Coit between Jereme and Lebanon will be replaced with this project which is scheduled to be complete early next year.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Brian C
New member
Username: Brianc

Post Number: 58
Registered: 06-2003
Posted on Wednesday, December 28, 2005 - 05:03 pm:   

It has been almost two months since grading started.. and lately I have not seen much work. Has something happened?
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 70
Registered: 10-2003
Posted on Friday, December 30, 2005 - 09:48 am:   

Thanks Brian for the post. Nothing has happened and the contractor is very busy installing the underground storm sewer. They started at Lebanon and are working their way north to College. Just this morning I noticed that they are already past CR 68.


If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Brian C
New member
Username: Brianc

Post Number: 59
Registered: 06-2003
Posted on Tuesday, January 03, 2006 - 02:34 pm:   

Thanks Hulon,
Phase 2 will include lighting/irrigation for the entire length of Coit as mentioned in the bid listing above?

Also, at one point Council mentioned a turn lane when going S. on Coit onto Jereme. Is that still going in (doesnt look like enough room plus there is a sprinkler line on top of the ground..not sure who put it there).

Thanks
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 71
Registered: 10-2003
Posted on Wednesday, January 04, 2006 - 01:23 pm:   

Correct, Phase 2 will provide irrigation and lighting along the entire length of the job.

Included in the construction of Phase 2 will be a southbound right turn lane installed on Coit Road at Jereme Trail. If you look at the screening wall along Coit Road at Jereme Trail you can see how it was constructed further away from Coit Road allowing room for the proposed turn lane.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon




 

Kenneth J Collins
New member
Username: Oakleyken

Post Number: 1
Registered: 11-2005
Posted on Tuesday, February 14, 2006 - 09:35 am:   

Mr. Webb,

Can you please provide an update on the construction on Coit between Main and El Dorado. Wasn't it supposed to be completed 2/7/06?
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 77
Registered: 10-2003
Posted on Tuesday, February 14, 2006 - 01:35 pm:   

Thanks Mr. Collins for the post. The contractor originally anticipated Coit Road north of Main to be opened by 2/7/06. Unfortunately conflicts with Southwestern Bell and TXU Electric have delayed the paving operations. As soon as the conflicts are adjusted by the appropriate utility company, the paving will commence. We anticipate the road will be opened north of Main Street sometime mid/late March 2006.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Brian C
New member
Username: Brianc

Post Number: 60
Registered: 06-2003
Posted on Tuesday, February 14, 2006 - 02:51 pm:   

Has the contractor provided an estimate for completion of Coit from Lebanon north? Thanks.
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 78
Registered: 10-2003
Posted on Wednesday, February 15, 2006 - 09:18 am:   

Coit from Lebanon north should be complete sometime mid/late March 2006 as well. Once complete, the current two way traffic traveling on the existing lanes of Coit from Jereme south to Lebanon will be relocated to the new north bound lanes of Coit so that the existing lanes can be removed and replaced.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Paul Konen
New member
Username: Pkonen

Post Number: 7
Registered: 03-2003
Posted on Thursday, March 23, 2006 - 10:48 am:   

Hulon, could we get an update? It looks to be close to doing a traffic switch so the existing lanes can be repaired.

Thanks
Paul
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 81
Registered: 10-2003
Posted on Friday, March 24, 2006 - 12:50 pm:   

Thanks Paul for the post. The contractor is still working on the new section of Coit from Rolater south and expects the traffic switch to occur in about 4 weeks. At that point the existing lanes will be removed and replaced.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Amelia Phillips
New member
Username: Ameliap

Post Number: 2
Registered: 03-2006
Posted on Thursday, March 30, 2006 - 12:43 pm:   

Mr. Webb,

Is there an update on the estimated completion date of Coit from Main to El Dorado? Or at least when you will be able to use Coit on that stretch?

Thank you
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 82
Registered: 10-2003
Posted on Friday, March 31, 2006 - 10:25 am:   

Thanks Amelia for the post. The contractor still has quite a bit of work to complete on Main Street and on Coit north of Main Street prior to opening that stretch to traffic. It is estimated that the remaining work will be complete sometime late April and the road reopened to traffic at that time. For now, only the intersection is being improved. The remaining section of Coit north to Eldorado will remain gravel.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Brian C
New member
Username: Brianc

Post Number: 64
Registered: 06-2003
Posted on Tuesday, May 30, 2006 - 10:22 am:   

1. What is the status of Coit from Jereme to Warren? There has been no change in the last 30 days. The intersection at Jereme is still rock.

2. Why is Coit north of Main being developed yet the remaining section South of Main is not?
 

Hulon Webb, Engineer
Moderator
Username: Hulon

Post Number: 88
Registered: 10-2003
Posted on Wednesday, May 31, 2006 - 09:02 am:   

Thanks Brian for the post.

1. During the excavation of the existing lanes of Coit Road from Jereme to Lebanon, it was discovered that the storm sewer under that section of Coit was damaged. Our Public Works Department is currently investigating the extent of damage so that the pipe can be replaced before the road is repoured.

2. It was intended to have both the north and south sections of Coit constructed with the Coit Road Project. Unfortunately, the property owner on the southwest corner of Coit and Main has refused to work with the city in dedicating the right-of-way so that Coit south of Main can be developed.

If you have any further questions, please feel free to contact me at (972) 335-5585 ext. 127.

Thanks, Hulon
 

Bryan Fritchie
New member
Username: Hogcall

Post Number: 5
Registered: 06-2006
Posted on Monday, June 26, 2006 - 12:42 pm:   

Above it was stated that the Coit & Main St intersection would be opened in late-April. It is now late-June and it appears to be far from done. Can someone provide a status update of Coit from 121 all the way to ElDorado? Thanks
 

Mark Bellissimo
New member
Username: Markbellissimo

Post Number: 1
Registered: 06-2006
Posted on Tuesday, June 27, 2006 - 03:09 pm:   

I am looking at building a home in Panther Creek and have been reading over this forum trying to get estimates, on what is going to happen to the roads in that area. I am really interested in the construction of coit road between eldorado and main street and when that might be completed?
 

Frank Jaromin, City Engineer
Moderator
Username: Frank_jaromin

Post Number: 201
Registered: 07-2003
Posted on Monday, July 10, 2006 - 09:09 am:   

The section of Coit Road north of Main Street was not included in the 2006 bond sale. Public Works will be placing asphalt over the existing road to help improve the roadway. This section of Coit Road has not been scheduled for construction at this time and is dependant on development occurring along it.

If you require further information please call me at 972-335-5585 ext. 129.

Frank Jaromin
City Engineer
 

KJC
New member
Username: Bogart06

Post Number: 1
Registered: 10-2006
Posted on Wednesday, November 29, 2006 - 08:25 pm:   

Any chance of increasing the speed limit on Coit between Main and Eldorado? The posted speed limit is 35 mph. I realize that stretch of Coit is gravel, but theres no homes, school zones, etc. Why the low posted speed limit? On Preston, the same stretch of road has a posted speed limit of 55 mph and it has residential side streets, businesses, and a church.
 

Brian Moen, Transportation Manager
Moderator
Username: Brian

Post Number: 295
Registered: 07-2001
Posted on Thursday, November 30, 2006 - 10:27 am:   

KJC,

While the roadways may appear to be the same, they are not. Coit has a much narrower width, the roadside is less forgiving, and the roadway surface is a chip seal over the gravel whereas Preston is asphalt.

Our trial runs have indicated that 35mph is a safe and prudent speed. We will be conducting a new speed study along this stretch next spring. That new study may or may not result in a change.

Thanks
Brian Moen
Transportaton Manager

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: