Todd Mundorff
New member
Username: Tmundorff

Post Number: 25
Registered: 01-2005
Posted on Monday, November 28, 2011 - 10:05 am:   

Do you know when the west side will open for 2 lanes each direction?
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 103
Registered: 06-2008
Posted on Wednesday, November 30, 2011 - 03:52 pm:   

TxDOT's contractor is still working on completing the west side. They have currently poured two of the proposed 3 lanes and still have to complete driveway and side street tie-ins as well as finishing left turn lanes. TxDOT's current estimate for placing traffic on the west side is February.
 

Leigh Ann Fields
New member
Username: Leigh6870

Post Number: 1
Registered: 01-2012
Posted on Sunday, January 01, 2012 - 04:24 pm:   

Hi, I'm looking at buying a home in Creekside in Preston and currently live out of state. Is there going to be a light built at Preston/Mockingbird Lane at the entrance?

(Message edited by admin on January 04, 2012)
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 70
Registered: 06-2010
Posted on Wednesday, January 04, 2012 - 11:45 am:   

The installation of traffic signals follows a nationally standardized process that traffic engineers must follow. There is a set of Traffic Signal Warrants that must be satisfied before a traffic signal can be installed, most of which are based on traffic volumes. Not every street can be given a traffic signal, so traffic counts are a very large factor in deciding which streets will be signalized (the busier streets should be signalized instead of less busy streets), and then again traffic volumes are used in prioritizing locations that are competing for the City’s limited funding.

Mockingbird Lane has been selected as the location of a future traffic signal. The next step is determining when it meets the warrants to actually have a signal installed. Mockingbird Lane intersects with Preston Road, which is a TxDOT roadway. Therefore, TxDOT will also need to approve the installation of a traffic signal at this location. TxDOT follows a strict process where a location cannot be signalized until it actually reaches the traffic volumes necessary to warrant the signal. The City evaluates a long list of locations each year with updated traffic volume counts to determine if the signal warrant volume thresholds are met, and then prioritizes the installation of a traffic signal based on available funding. The most recent counts and signal warrant analysis was conducted at this location in the fall of 2011 and the results indicated that it does not meet the signal warrant volume thresholds. Therefore, the City will continue to evaluate this location each year to determine when it meets the signal warrant volume thresholds to move it up on the traffic signal installation priority list.

I also wanted to let you know that the TxDOT Preston Road widening project between US 380 and Main Street is nearing completion. It is in the final stages, which is to complete and open the six-lane divided roadway on Preston Road south of Mockingbird Lane between Eldorado Parkway and Main Street in the spring. The completion of this project will significantly improve the traffic conditions on Preston Road.

If you have any further questions, please let us know.

Thanks!

Shelly Lang
Senior Traffic Engineer
 

Todd Mundorff
New member
Username: Tmundorff

Post Number: 26
Registered: 01-2005
Posted on Friday, January 27, 2012 - 04:05 pm:   

Any new information regarding the opening of south bound lanes on the west side? I havent seen much activity at all in Jan.
 

Harley Rubin
New member
Username: Addude13

Post Number: 1
Registered: 01-2012
Posted on Tuesday, January 31, 2012 - 04:43 pm:   

Online and newspaper reports claim that the Preston project (between 380 and Main) will be done on 2/1. It does not appear that those reports are accurate.

Can you please provide an update on the schedule and completion?
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 106
Registered: 06-2008
Posted on Thursday, February 02, 2012 - 04:48 pm:   

The work on Preston Road in January has been slower. In addition to being delayed due to weather for a few days, the contractor is preparing for the paving crew to come and finish the turn lanes and driveways. The paving crew is currently on another project. They are expected to be on the project starting February 6. Once the turn lanes are completed, we can work with the contractor to open, at least partially, the southbound lanes.

TxDOT has updated the competion date to May 2012. Newspaper and online reports will start reflecting that information.
 

Jim Page
New member
Username: Hawaiijim

Post Number: 11
Registered: 05-2010
Posted on Monday, March 12, 2012 - 01:46 pm:   

There has been virtually no work done on this project for quite some time. The winter has been exceedingly mild, so what is causing the delays? Why can't TxDOT move this project up?

(Message edited by admin on March 22, 2012)
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 107
Registered: 06-2010
Posted on Thursday, March 22, 2012 - 11:21 am:   

We have reached a point during construction that it is not quite as obvious that work is being progressed. Many of the larger items of work are done, so much of the big equipment is gone. There are still crews on Preston pushing forward toward completion, but they are smaller crews and more spread out along the project.
We would all like them to finish faster. TxDOT provides a certain number of days to complete the project before penalties begin. The contractor is expected to complete the project before the contract time runs out. We will continue to work with TxDOT to keep the project moving towards completion.
Again, we apologize for the inconvenience during construction, but when complete, the construction pains we have experienced should be well worth it. We are getting close. Things should get significantly better in the next couple of months as the Preston Road project nears completion.
Please feel free to contact me should you have any further questions.
Jason Brodigan, P.E.
Senior Civil Engineer
 

HAKIM S. WILLIAMS
New member
Username: Hak1906

Post Number: 3
Registered: 11-2005
Posted on Wednesday, April 11, 2012 - 10:53 am:   

I see on the recent engineering report that the completion date has changed from 5-1-12 to 6-29-12. Can you provide us residents who deal with the traffic on this section everyday and it's backups, what has occured that the project has gone from the end of 2011 to March 2012 to 5-1-12 to now basically the end of June 2012. The weather has not been affected and I don't know if utilities, permits, etc.. has been an issue but any insight you all could provide would be much appreciated.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 111
Registered: 06-2008
Posted on Thursday, April 19, 2012 - 08:29 am:   

Apologize for the delayed response. We have been working with TxDOT and Sinacola on some minor construction changes. While these changes were being worked on, Sinacola was pursuing the completion of Custer Road. We are back on track and have some changes for Preston Road scheduled for next week which should help traffic flow and allow Sinacola to push the project to completion. We are now optimistic that it may not take until late June to complete the project.
 

Todd Mundorff
New member
Username: Tmundorff

Post Number: 28
Registered: 01-2005
Posted on Friday, April 13, 2012 - 11:23 am:   

Is there an official opening date in May from TxDOT? The pace of work has been unconscionably slow this entire year.
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 122
Registered: 06-2010
Posted on Tuesday, April 24, 2012 - 09:24 am:   

We have been working with TxDOT and Sinacola on some minor construction changes. While these changes were being worked on, Sinacola was pursuing the completion of Custer Road. We are back on track and have some changes for Preston Road scheduled for next week which should help traffic flow and allow Sinacola to push the project to completion. We are now optimistic that it may not take until late June to complete the project.
Jason Brodigan
Senior Engineer
 

Sriram Iyer
New member
Username: Sriramiyer

Post Number: 6
Registered: 06-2005
Posted on Wednesday, May 02, 2012 - 07:42 am:   

Now that part of Preston Road between Eldorado and Main Street is open, I was wondering if the intersection of Preston and Main will be finished now or will it be worked on when the widening of Main Street to Custer begins. Because looks like there is a lot of work to be done for about 200 meters on Preston north of Main.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 113
Registered: 06-2008
Posted on Wednesday, May 09, 2012 - 10:33 am:   

Construction of all of the lanes on Preston will be completed with the current project. No work on Preston Road is included with the Main St. project.
 

Jesse Hardin
New member
Username: Jahardin

Post Number: 14
Registered: 08-2007
Posted on Wednesday, May 09, 2012 - 10:52 am:   

Is there an updated completion date for the work at the intersection and just north of Eldorado/Main?
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 144
Registered: 06-2010
Posted on Wednesday, May 16, 2012 - 02:42 pm:   

Preston Road [SH 289] (CIP05-0031) Main St to US 380
Project Manager: Jason Brodigan
Project Description: Replace the existing two-lane asphalt roadway with a six-lane divided concrete roadway. Project includes paving and drainage.
Project Update: Sinacola is working on completing southbound lanes between Main Street and Preston Manor.
Construction End: 6/29/2012
Estimated Construction Cost: $10,166,838

Here is the link to the Monthly Report…
http://www.friscotexas.gov/departments/engineering/Documents/Monthly%20Report.pd f
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 145
Registered: 06-2010
Posted on Wednesday, May 16, 2012 - 02:52 pm:   

Preston Road [SH 289] (CIP05-0031) Main St to US 380
Project Manager: Jason Brodigan
Project Description: Replace the existing two-lane asphalt roadway with a six-lane divided concrete roadway. Project includes paving and drainage.
Project Update: Sinacola is working on completing southbound lanes between Main Street and Preston Manor.
Construction End: 6/29/2012
Estimated Construction Cost: $10,166,838

Here is the link to the Monthly Report…
http://www.friscotexas.gov/departments/engineering/Documents/Monthly%20Report.pd f
 

Jesse Hardin
New member
Username: Jahardin

Post Number: 15
Registered: 08-2007
Posted on Tuesday, June 19, 2012 - 10:53 am:   

It sure appears as though Main Street and Preston intersection work is stalled again. Is there a new completion date for this part of the project?

Why is this so difficult to complete? It seems as though the same big hole in the middle of the road has been in place for almost a year.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 115
Registered: 06-2008
Posted on Friday, June 22, 2012 - 11:17 am:   

Work has resumed on Preston Road and we are not anticipating any further delays to the completion of the project. The project is now expected to be completed by August 1, 2012.
 

Todd Mundorff
New member
Username: Tmundorff

Post Number: 29
Registered: 01-2005
Posted on Tuesday, June 26, 2012 - 08:18 am:   

Will the (new) northbound right turn only lane and southbound left turn only lanes on westbound Eldorado @ Preston also be complete by Aug 1st.
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 118
Registered: 06-2008
Posted on Tuesday, July 03, 2012 - 11:29 am:   

The new turn lanes on Eldorado are expected to be completed along with the rest of Preston Road by August 1.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: