Timeline for Coit between Main and Eldorado?

Jason Brodigan, Sr. Civil Engineer
Username: Jason_brodigan

Post Number: 91
Registered: 06-2008
Posted on Friday, July 08, 2011 - 04:30 pm:   

We are currently working on the design for the reconstruction of Coit to 4 lanes from Main St to north of Eldorado. We are expecting to start construction in Spring 2012 and the project is expected to take approximately 6-8 months to complete.

Add Your Message Here
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Options: Enable HTML code in message
Automatically activate URLs in message