David Lacefield
New member
Username: Dlacefie

Post Number: 7
Registered: 02-2007
Posted on Monday, February 07, 2011 - 04:52 pm:   

What is the status of plans to connect the gap in Stonebrook Pkwy between Legacy Drive and Longhorn Trail?
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 72
Registered: 06-2008
Posted on Wednesday, February 09, 2011 - 11:37 am:   

Stonebrook Parkway from Legacy Drive to Longhorn Trail has been split into two projects.

Phase 1: Legacy Drive to Fighting Eagles.
This project has been awarded to Texas Sterling Construction and should begin in the next couple of weeks, weather permitting. Construction is expected to be complete by the end of 2011.

Phase 2: Fighting Eagles to Longhorn Trail.
US Corps of Engineers and BNSF railroad permitting is ongoing and is the reason this phase is behind Phase 1. Design of Phase 2 is 90% complete. Construction is expected to begin in early 2012 and take 2 years to complete.
 

Reid Johns
New member
Username: Rl_johns

Post Number: 1
Registered: 09-2011
Posted on Tuesday, September 06, 2011 - 10:27 am:   

Is there any update on this section of Stonebrook Pkwy?
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 100
Registered: 06-2008
Posted on Tuesday, September 06, 2011 - 03:54 pm:   

Phase 1 is expected to be completed in October.

Phase 2 is expected to begin in early 2012 and take 2 years to complete.
 

Techie
New member
Username: Mtechie

Post Number: 1
Registered: 11-2011
Posted on Wednesday, November 02, 2011 - 09:37 am:   

When is Stonebrook Pkwy opening from Legacy to DNT? It looks complete but is still blocked.

(Message edited by admin on November 04, 2011)
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 575
Registered: 02-2003
Posted on Friday, November 04, 2011 - 09:50 am:   

The connection to the Dallas North Tollway is not expected to be completed until Spring 2014. The project has been split into two phases. Phase 1, which extends from Legacy to Fighting Eagles, is nearing completion and is expected to be open in the next couple of weeks. Phase 1 was accelerated to provide additional access to the new Legacy Christian Academy High School which is scheduled to open in late 2011. In addition, the Phase 1 project does not require US Corps of Engineers permits. Phase 2, Fighting Eagles to Longhorn Trail, which will complete the connection to the Dallas North Tollway, is scheduled to begin in Spring 2012 and take 2 years to construct.
 

biju
New member
Username: Hiddencove

Post Number: 2
Registered: 12-2011
Posted on Sunday, December 04, 2011 - 01:47 pm:   

Stonebrook parkway & Hackberry road

Is there any expansion plans for above mentioned road that leads to Hidden Cove Community.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 576
Registered: 02-2003
Posted on Friday, December 09, 2011 - 03:24 pm:   

The developer for Hidden Cove Phase 4 (in the town of Hackberry) is improving a section of Stonebrook Parkway. Traffic is currently being served by an asphalt detour while the permanent street is being constructed. When complete, Stonebrook will consist of a 36 wide street with one lane of traffic in each direction from where the concrete pavement currently ends to just north of the intersection of Stonebrook and Hackberry Creek Park Road.
 

Lmonday69
New member
Username: Lmonday69

Post Number: 1
Registered: 05-2012
Posted on Monday, May 21, 2012 - 09:16 am:   

"Construction of the next section of Stonebrook Parkway, which will provide a connection between Legacy Drive and Dallas Parkway, is slated to begin in March of 2012."

Is that still the plan?

(Message edited by admin on May 30, 2012)
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 158
Registered: 06-2010
Posted on Wednesday, May 30, 2012 - 10:54 am:   

The project has been delayed because we are still waiting on an agreement with the railroad. Construction is tentatively scheduled to begin in September of 2012.



Joel W. Fitts, P.E., PTOE
Senior Traffic Engineer
 

Brian C
New member
Username: Brianc

Post Number: 155
Registered: 06-2003
Posted on Tuesday, September 25, 2012 - 11:15 am:   

Checking on the latest schedule...
 

Jason Brodigan, Sr. Civil Engineer
Moderator
Username: Jason_brodigan

Post Number: 120
Registered: 06-2008
Posted on Tuesday, October 02, 2012 - 08:45 am:   

The City has opened bids for the Stonebrook Parkway project between Longhorn and Fighting Eagles and the award of the contract to the low bidder is on the October 2nd City Council Agenda. We are still waiting final approval from the railroad to begin construction; however, construction is expected to begin in November.
 

Yvette Wallace
New member
Username: Ywallac

Post Number: 2
Registered: 06-2012
Posted on Thursday, November 01, 2012 - 01:53 pm:   

How long is the construction expected to last on Stonebrook Pkwy between Preston and the Tollway?

(Message edited by admin on November 06, 2012)
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 274
Registered: 06-2010
Posted on Tuesday, November 06, 2012 - 03:08 pm:   

The contractor has, by contract, until November 18, 2014, to complete the construction of the project.

Arthur Hartle, P.E.
Senior Civil Engineer
 

TARIQ ADATIA
New member
Username: Tadatia

Post Number: 1
Registered: 11-2012
Posted on Thursday, November 08, 2012 - 09:48 am:   

Has a contractor been approved? If so, has construction started? Are the approvals in place from the railroad?
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 278
Registered: 06-2010
Posted on Monday, November 12, 2012 - 03:12 pm:   

The contractor has, by contract, until November 18, 2014, to complete the construction of the project.

Arthur Hartle, P.E.
Senior Civil Engineer
Engineering Services
 

Brian C
New member
Username: Brianc

Post Number: 156
Registered: 06-2003
Posted on Tuesday, April 02, 2013 - 06:52 am:   

It appears the project has started, is there a new schedule?
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 379
Registered: 06-2010
Posted on Tuesday, April 02, 2013 - 01:33 pm:   

The end date for the project is November 2014.
 

Raghu R
New member
Username: Flthere

Post Number: 2
Registered: 07-2014
Posted on Thursday, August 21, 2014 - 05:18 pm:   

I see the last response was little over a year but we are approaching November in couple months. Is the project on track to be finished by November 2014? Thank you.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: