Are there plans to improve the Dallas Parkway once the Tollway is completed? Will it be widened to three lanes?

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 425
Registered: 02-2003
Posted on Thursday, July 19, 2007 - 12:24 pm:   


There are plans to widen the frontage road to 3 lanes from SH 121 to Eldorado. This expansion will occur in phases.

The first project is from SH 121 to Warren. This project has federal funding and is scheduled to begin design in late 2007 or early 2008. I would expect construction to be finished by 2010.

The project from Warren to Eldorado is a project that we have submitted for funding through Collin County. A new Collin County bond election is planned for this November. If this project gets funded through this bond program, construction would probably start in 2010.

I would also expect the frontage roads to be widened to three lanes from Eldorado to US 380. Currently, there is no timeline established for that expansion.

Brian Moen
Asst. Dir. Engineering Services/Transportation

Add Your Message Here
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Options: Enable HTML code in message
Automatically activate URLs in message