Widening of Lebanon between 423 and 4... Log Out | Topics | Search
Moderators | Register | Edit Profile

City of Frisco Question and Answer Board » Frisco Q & A » Widening of Lebanon between 423 and 4th army? « Previous Next »

  Thread Last Poster Posts Pages Last Post
Model rocketsTodd Renshaw, Chief 01-19-09  10:40 am
  Start New Thread        

Author Message
 

Kyle Rabinowitz
New member
Username: Kalpern

Post Number: 1
Registered: 05-2007
Posted on Wednesday, May 30, 2007 - 03:53 pm:   

When is this going to start and when is the anticipated finish?

Also, what is being built south of Lebanon and 4th army? Is that a new road?
 

Luke Jalbert, EIT
Moderator
Username: Luke_jalbert

Post Number: 12
Registered: 07-2006
Posted on Wednesday, June 06, 2007 - 02:18 pm:   

Mr. Rabinowitz,

The engineer for this project is currently revising the plans. The design changes should be completed in early September. Construction will start in October and take approximately nine months.

A new subdivision, Hills of Kingswood, is being built south of Lebanon near 4th Army. They are building Rock Creek Parkway as part of that project.
 

bobparr
New member
Username: Bobparr

Post Number: 2
Registered: 02-2007
Posted on Friday, July 06, 2007 - 04:50 pm:   

Do you know what builders will be building homes in the Hills of Kingswood?
 

Scott Ingalls, Zoning & Subdivision Admi
Moderator
Username: Scott_ingalls

Post Number: 360
Registered: 06-2003
Posted on Monday, July 09, 2007 - 10:29 am:   

Bobparr,

At this time we do not know who the builders will be. The developer has indicated that part of the development will be for custom builders but as of now they have not indicated any specific builders.

Scott Ingalls
Zoning & Subdivision Administrator
 

Kyle Rabinowitz
New member
Username: Kalpern

Post Number: 2
Registered: 05-2007
Posted on Tuesday, July 10, 2007 - 12:41 am:   

Where is Rock Creek Parkway going to go? Are we going to have another way out of West Frisco??
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 421
Registered: 02-2003
Posted on Thursday, July 12, 2007 - 07:23 am:   

Kyle,

Rock Creek Parkway will lead to the Hills of Kingwood subdivision and other developments just south of Lebanon. It will not connect to the Colony.

Thanks
Brian Moen
Asst. Dir. of Engineering Services/Transportation
 

Paul Sukhu
New member
Username: Paul_s

Post Number: 14
Registered: 12-2004
Posted on Thursday, July 12, 2007 - 10:50 am:   

There is now major construction (earth work) happening on Lebanon that started a few days ago. This is on the south side of Lebanon at Beacon Hill Drive, in the middle of Lone Star Ranch.

Can you please describe this project?

Thanks.
 

Dr Burke
New member
Username: Idoc4life

Post Number: 1
Registered: 07-2007
Posted on Sunday, July 29, 2007 - 10:53 am:   

What is the plan for the intersection of Rock Creek Parkway and Lebanon? Will there possibly be a traffic light at this intersection?
 

Brian Moen, Asst. Dir. Eng. /Transp
Moderator
Username: Brian

Post Number: 320
Registered: 07-2001
Posted on Monday, July 30, 2007 - 08:32 pm:   

A traffic signal will be constructed with the widening of Lebanon in this area.

Thanks
Brian Moen
Asst. Dir. Engineering Services
 

Kyle Rabinowitz
New member
Username: Kalpern

Post Number: 3
Registered: 05-2007
Posted on Wednesday, August 01, 2007 - 03:04 pm:   

There is a sign that says Lebanon will be closed at Rockcreek Parkway on August 11 - Detour to Stonebrook. Is that just for the day or is that long term?
 

Paul Sukhu
New member
Username: Paul_s

Post Number: 16
Registered: 12-2004
Posted on Friday, August 31, 2007 - 09:20 am:   

Is the "widening of Lebanon" project still on track for an October construction start?

Thanks.
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 75
Registered: 06-2003
Posted on Tuesday, September 04, 2007 - 12:36 pm:   

Spiars Engineering is currently designing the widening of Lebanon Road from two to four lanes. Engineering plans are being revised to incorporate new subgrade requirements. Construction is pending ROW acquisition and revision of plans to incorporate new subgrade requirements. The project is expected to bid in October, and construction to start in November 2007. Construction will require approximately 15-18 months for construction.
 

Dr Burke
New member
Username: Idoc4life

Post Number: 2
Registered: 07-2007
Posted on Monday, November 19, 2007 - 10:41 am:   

Any updates on this project?
 

Cissy Sylo, Director of Engineering Serv
Moderator
Username: C_sylo

Post Number: 79
Registered: 06-2003
Posted on Monday, November 19, 2007 - 02:25 pm:   

The project bid is anticipated to be awarded at the December 4th City Council meeting.
 

suresh munipalli
New member
Username: Munipalli

Post Number: 3
Registered: 02-2006
Posted on Saturday, January 19, 2008 - 09:53 pm:   

Had this project been awarded,if so when are we expecting the actual work to be started.
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 492
Registered: 02-2003
Posted on Monday, January 21, 2008 - 09:12 am:   

Per the Engineering Services montly report which can be found on the City's web site here:

http://www.friscotexas.gov/Departments/engineering/index.aspx?id=2027

Lebanon Parkway (FM 423 4th Army) Spiars Engineering designed the widening of
Lebanon Road from two to four lanes (eastbound lanes). Engineering plans were revised to
incorporate new subgrade requirements. The project was bid on October 16, 2007 and
Rodman was the lowest bidder. Construction is expected to start in January 2008 and is
expected to take approximately 15-18 months.
 

Nidhi
New member
Username: Nnidhi

Post Number: 1
Registered: 03-2008
Posted on Monday, March 10, 2008 - 11:41 am:   

Any update on this...?
 

Curt Balogh, Spec. Asst. to the City Mgr
Board Administrator
Username: Admin

Post Number: 511
Registered: 02-2003
Posted on Tuesday, March 11, 2008 - 03:02 pm:   

Per the Engineering Services monthly report (which is updated every month) and can be found on the City's web site here:

http://www.friscotexas.gov/Departments/engineering/index.aspx?id=2027

Lebanon Parkway (FM 423 4th Army) Spiars Engineering designed the widening of
Lebanon Road from two to four lanes (eastbound lanes). Engineering plans were revised to
incorporate new subgrade requirements. The project was bid on October 16, 2007 and
Rodman was the lowest bidder. Construction has started and is expected to take
approximately 15-18 months.
 

Kyle Rabinowitz
New member
Username: Kalpern

Post Number: 4
Registered: 05-2007
Posted on Thursday, January 08, 2009 - 01:09 am:   

Any update? It seemed like it was moving forward very fast and then everything stopped. When will this be done?
 

Michael Bulla, Special Project Manager
Moderator
Username: Michael_bulla

Post Number: 18
Registered: 01-2008
Posted on Friday, January 16, 2009 - 10:13 am:   

Kyle,
We did suffer a delay while a solution could be reached on how to work around several franchise utilities contained within what is now the median of Lebanon. The contractor has indicated crews would be resuming the paving work the first of next week (1/19/09). If the weather cooperates, I would expect to see some concrete hitting the ground in early February. Crews are currently working at the major intersections on the signal lights. I will repost next week when we are certain the paving crews have arrived. Thank you, Michael
 

Carl Gruenberg
New member
Username: Ceej

Post Number: 1
Registered: 05-2009
Posted on Friday, May 29, 2009 - 11:07 pm:   

Hey looks like the new section of lebanon is complete, any idea when we will be driving our cars on it?

(Message edited by perry on June 01, 2009)
 

Perry Harts, Moderator
Board Administrator
Username: Perry

Post Number: 95
Registered: 06-2002
Posted on Monday, June 01, 2009 - 10:38 am:   

The contractor has almost completed all work on this project. Some of the outstanding items are the guardrail near the bridge and pavement markings on the left turn lane to Teel Parkway. Once these items are completed, the contractor will switch eastbound traffic on the newly constructed pavement (on one of the lanes) and this is expected to occur on June 4.

After the switch, the contractor will complete work at the crossovers, install remaining traffic signs and pavement markings, landscaping and cleanup work. All work should be completed by the 2nd week in June weather permitting. Sorry for the inconvenience but this will certainly make traffic through this area better once completed.

Thank you for your patience and call me if you have any questions.


Toyin Fawehinmi, P.E.
City of Frisco - Engineering Services Department
6101 Frisco Square Blvd., 3rd Floor
Frisco, Texas 75034
Office (972) 292 5439
 

LibR
New member
Username: Lreed

Post Number: 10
Registered: 02-2007
Posted on Tuesday, June 09, 2009 - 12:48 pm:   

Is there any reason why the sidewalk on both the north and south side of Lebanon stop short of the bridge (by BF Philips Park). It is very dangerous for pedestrians to get from the west side of the bridge all the way to Stewart Creek Estates where the side walk continues (or vice versa). I've seen numerous runners and bikers dodging traffic in this area and seems like it is only a matter of time before a terrible accident happens.
 

Perry Harts, Moderator
Board Administrator
Username: Perry

Post Number: 98
Registered: 06-2002
Posted on Tuesday, June 09, 2009 - 02:09 pm:   

Libr

The reason is that when Lebanon Road was constructed the sidewalks were not part of the construction project. The City is actually working on plans and bid requirements to extend the walk from where it stops at Stewart Creek Estates on the east to Teel Parkway on the north side of the road. I would anticipate that the construction should be completed by the end of the year.

Feel free to contact me if you have further questions.

Dudley Raymond
Parks Planning and Business Development Manager
 

Beth Woodruff
New member
Username: Beth_woodruff

Post Number: 4
Registered: 10-2005
Posted on Wednesday, March 24, 2010 - 09:30 pm:   

What is the new projected date for the addition of a traffic light at the intersection of Lebanon and Rock Creek?
 

Perry Harts, Moderator
Board Administrator
Username: Perry

Post Number: 188
Registered: 06-2002
Posted on Thursday, March 25, 2010 - 10:03 am:   

Beth,

There is not a projected date at this time. It will be dependent on the rate of development in the area along Rock Creek south of Lebanon. As more homes are built in this area, the traffic volume will increase and warrant a signal. Once warranted, we will look to move forward with construction.

Thanks
Brian Moen
Assistant Director of Engineering Services
 

LSR-AR Resident
New member
Username: Brigopens

Post Number: 5
Registered: 06-2011
Posted on Friday, August 28, 2015 - 10:34 pm:   

What is going on with the medians on Lebanon now between 4th army and the railroad bridge?
 

Ben Brezina, Assistant to the City Manag
Moderator
Username: Ben_brezina

Post Number: 806
Registered: 06-2010
Posted on Friday, September 11, 2015 - 03:55 pm:   

A 12-inch reuse water pipeline is being installed from 4th Army (actually from Stewart Creek Wastewater Treatment Plant) to John Hickman to provide irrigation water for development along DNT.

Add Your Message Here
Post:
Username: Posting Information:
This is a private posting area. Only registered users and moderators may post messages here.
Password:
Options: Enable HTML code in message
Automatically activate URLs in message
Action: